Pattern Consistent with Contract Splitting
Multiple similar contracts to the same contractor/DEO just under a threshold in a short window.
This is a statistical anomaly or indicator worth examining — not proof of wrongdoing, fraud, or corruption against any person.
Indicator: 3 contracts awarded to BELL CONST by the same office started within 7 days, each between ₱42.5M and ₱50M (just under the ₱50M threshold), with 3 in the same municipality. It is possible these are separate projects in different locations or phases within the same city, as is common for flood control works.
Only contractors and government agencies named in public procurement records are shown. Private individuals are not named.
Satellite before / after
Named in this indicator? Respond or report an error · Corrections policy
Project completion
Schedule fields from DPWH transparency portal records and the Sumbong sa Pangulo flood-control list — not inferred beyond those columns.
| Project | Prog. | Target end | Actual end | Days late | Status |
|---|---|---|---|---|---|
| Construction of Flood Control Structure, Sitio Libis Creek, Barangay San Jose, Antipolo City23DN0067Flood control | 100% | December 8, 2023 | December 8, 2023 | — | completedsumbong source |
Start: March 14, 2023 · Source fetched October 21, 2026
Rule Definition
≥3 contracts within 120 days, each 85–100% of ₱50M threshold, similar titles.
Triggering Data & citations
Cluster of contracts just under procurement threshold with similar scope
{
"deo": "Rizal 1st District Engineering Office",
"contractId": "23DN0067",
"contractor": "BELL CONST",
"windowDays": 120,
"clusterSize": 3,
"thresholdPhp": 50000000,
"contractCostPhp": 48999253.95,
"averageTitleSimilarity": 0.908597975791964
}Source documents
Possible Innocent Explanations
- Legitimate multi-lot procurement
- Different sites under same program