Love the Philippines

Indicator worth a closer look. Not an accusation or a finding of wrongdoing.

Ito ay istatistikong anomalya o indikador na dapat suriin — hindi patunay ng maling gawain, pandaraya, o katiwalian laban sa sinumang tao.

AI-verified / Na-verify ng AI Data as of October 21, 2026

Duplicate or Near-Duplicate Projects

Very similar descriptions within ~100m or identical coordinates across contracts/years.

This is a statistical anomaly or indicator worth examining — not proof of wrongdoing, fraud, or corruption against any person.

Indicator: contracts 24DL0064 and 23DL0089 have near-identical descriptions about 240 m apart (funding years 2023, 2024; ₱67.55M, ₱44.10M). Worth checking whether they cover the same works. It is possible that the second project is a continuation or additional phase of the first, but only one was labeled as a package.

Public record entityConstruction of Flood Control and Drainage Structure along Pipisik River, Gumaca, Quezon, Package A
LocationGUMACA (QUEZON), QUEZON, Region IV-AContract 23DL0089
Amount₱44,100,000.00 sumbong source

Only contractors and government agencies named in public procurement records are shown. Private individuals are not named.

Satellite before / after

Loading satellite imagery…

Named in this indicator? Respond or report an error · Corrections policy

Project completion

Schedule fields from DPWH transparency portal records and the Sumbong sa Pangulo flood-control list — not inferred beyond those columns.

Reported complete (DPWH): 1Ongoing: 0Delayed: 0Status unknown: 0
ProjectProg.Target endActual endDays lateStatus
Construction of Flood Control and Drainage Structure along Pipisik River, Gumaca, Quezon, Package A23DL0089Flood control100%December 3, 2023September 13, 2023No target date from DPWH, so lateness cannot be computedcompletedsumbong source

Start: March 9, 2023 · Source fetched October 21, 2026

Rule Definition

Title similarity + distance or shared coordinates within municipality.

Triggering Data & citations

Similar project description near another contract in the same municipality

{
  "contractId": "23DL0089",
  "fundingYear": 2023,
  "municipality": "GUMACA (QUEZON)",
  "distanceMeters": 239.8151476613853,
  "titleSimilarity": 0.9777777777777777
}

Possible Innocent Explanations

  • Phased construction seasons
  • Upstream/downstream segments recorded separately

Connected records

Where this project sits

Place (PSGC)
Region IV-A (CALABARZON)QuezonGumacaButaguin
Storms whose wind field reached it
Nokaen 2026Fung-Wong 2025Fengshen 2025Bualoi 2025Man-Yi 2024
Hazard exposure
Active fault5.6 km to mapped traceGEM Foundation (Philippines catalogue within GEM Global Active Faults)Flood (100-yr rain)outside mapped flood zonesUP NOAH Center / DOST-PAGASA (Project NOAH)Landslideoutside mapped landslide zonesUP NOAH Center / UP NIGS (Project NOAH)Storm surgeinundated from SSA1 (2.01-3 m)UP NOAH Center / DOST-PAGASA (Project NOAH)Full hazard check →
El Niño outlook (province)
Dry conditions likelyPAGASA · 2026-10-07El Niño readiness →

Exposure to a storm, hazard or drought outlook is context, not a finding about the project.