Pattern Consistent with Contract Splitting

Multiple similar contracts to the same contractor/DEO just under a threshold in a short window.

This is a statistical anomaly or indicator worth examining — not proof of wrongdoing, fraud, or corruption against any person.

Indicator: 5 contracts awarded to JFR CONST INC FORMERLY:JFR CONST by the same office started within 43 days, each between ₱42.5M and ₱50M (just under the ₱50M threshold), with 4 in the same municipality. It is possible that these are separate flood control projects needed in different barangays or along different rivers.

Public record entityConstruction of Flood Control Structures along Tabawan Creek (Phase II), Brgy. Tabawan, Calbayog City, Samar
LocationCALBAYOG CITY (SAMAR (WESTERN SAMAR)), SAMAR (WESTERN SAMAR), Region VIIIContract 22IJ0043
Amount₱48,637,574.32 sumbong source

Only contractors and government agencies named in public procurement records are shown. Private individuals are not named.

Satellite before / after

Loading satellite imagery…

Named in this indicator? Respond or report an error · Corrections policy

Project completion

Schedule fields from DPWH transparency portal records and the Sumbong sa Pangulo flood-control list — not inferred beyond those columns.

Reported complete (DPWH): 1Ongoing: 0Delayed: 0Status unknown: 0
ProjectProg.Target endActual endDays lateStatus
Construction of Flood Control Structures along Tabawan Creek (Phase II), Brgy. Tabawan, Calbayog City, Samar22IJ0043Flood control100%October 28, 2022October 28, 2022No target date from DPWH, so lateness cannot be computedcompletedsumbong source

Start: February 8, 2022 · Source fetched October 21, 2026

Rule Definition

≥3 contracts within 120 days, each 85–100% of ₱50M threshold, similar titles.

Triggering Data & citations

Cluster of contracts just under procurement threshold with similar scope

{
  "deo": "Samar 1st District Engineering Office",
  "contractId": "22IJ0043",
  "contractor": "JFR CONST INC FORMERLY:JFR CONST",
  "windowDays": 120,
  "clusterSize": 5,
  "thresholdPhp": 50000000,
  "contractCostPhp": 48637574.32,
  "averageTitleSimilarity": 0.9093892042595715
}

Possible Innocent Explanations

  • Legitimate multi-lot procurement
  • Different sites under same program

Connected records

Where this project sits

Place (PSGC)
Region VIII (Eastern Visayas)SamarCity of CalbayogGuinbaoyan Norte
Storms whose wind field reached it
Nokaen 2026Koto 2025Fung-Wong 2025Kalmaegi 2025Fengshen 2025
Hazard exposure
Active fault10.5 km to mapped traceGEM Foundation (Philippines catalogue within GEM Global Active Faults)Flood (100-yr rain)highUP NOAH Center / DOST-PAGASA (Project NOAH)Landslideoutside mapped landslide zonesUP NOAH Center / UP NIGS (Project NOAH)Storm surgenot inundated even at SSA4 (>5 m)UP NOAH Center / DOST-PAGASA (Project NOAH)Full hazard check →
El Niño outlook (province)
Drought / dry spell likelyPAGASA · 2026-11-03El Niño readiness →