14 published flags on records linked to Banna and the LGUs under it. A flag is an automated anomaly that reviewers checked before publishing: a question worth asking, not a finding of wrongdoing.
- C1 · Contractor Concentration (Flood Control)Alpha & Omega Gen Contractor & Development CorpContractor (applies to all its work) · contractor Alpha & Omega Gen Contractor & Development Corp
- C1 · Contractor Concentration (Flood Control)Alpha & Omega Gen Contractor & Development CorpContractor (applies to all its work) · contractor Alpha & Omega Gen Contractor & Development Corp
- C5 · Pattern Consistent with Contract SplittingConstruction of Flood Control Structure, Laoag River Basin and Sabo Flood Control Structure Along Lading River, Barangay Caray, Sitio Lading 2, Nueva Era, Ilocos NorteDPWH project · contractor Djcm Const Corp Formerly: Djcm Const
- C7 · High Concurrent Workload for One ContractorAlpha & Omega Gen Contractor & Development CorpContractor (applies to all its work) · contractor Alpha & Omega Gen Contractor & Development Corp
- C7 · High Concurrent Workload for One ContractorSt Matthew Gen Contractor & Development CorpContractor (applies to all its work) · contractor St Matthew Gen Contractor & Development Corp
- C5 · Pattern Consistent with Contract SplittingConstruction of Flood Control Structure, Laoag River Basin and Sabo Flood Control Structure Along Cabittauran River (Left Bank), Barangay Cabittauran, Sitio Baetan 1, Nueva Era, Ilocos NorteDPWH project · contractor Djcm Const Corp Formerly: Djcm Const
- C5 · Pattern Consistent with Contract SplittingConstruction of Flood Control Structure, Laoag River Basin and Sabo Flood Control Structure Along Lading River, Barangay Caray, Sitio Lading 1, Nueva Era, Ilocos NorteDPWH project · contractor Djcm Const Corp Formerly: Djcm Const
- C5 · Pattern Consistent with Contract SplittingConstruction of Flood Control Structure, Laoag River Basin and Sabo Flood Control Structure Along Cabittauran River (Left Bank), Barangay Sto. Nino, Sitio Nalibegan 1, Nueva Era, Ilocos NorteDPWH project · contractor St Timothy Const Corp
- C5 · Pattern Consistent with Contract SplittingConstruction of Flood Control Structure, Laoag River Basin and Sabo Flood Control Structure Along Cabittauran River (Right Bank), Barangay Cabittauran, Sitio Caduyungan 2, Nueva Era, Ilocos NorteDPWH project · contractor St Timothy Const Corp
- C5 · Pattern Consistent with Contract SplittingConstruction of Flood Control Structure, Laoag River Basin and Sabo Flood Control Structure Along Cabittauran River (Right Bank), Barangay Sto. NiñO, Sitio Nalibegan 2, Nueva Era, Ilocos NorteDPWH project · contractor St Timothy Const Corp
- C7 · High Concurrent Workload for One ContractorSt Timothy Const CorpContractor (applies to all its work) · contractor St Timothy Const Corp
- C5 · Pattern Consistent with Contract SplittingConstruction of Flood Control Structure Along Sinigpit Creek (Right Bank), Barangay Caray, Sitio Sinigpit 1, Nueva Era, Ilocos NorteDPWH project · contractor St Matthew Gen Contractor & Development Corp
- C5 · Pattern Consistent with Contract SplittingConstruction of Flood Control Structure, Laoag River Basin and Sabo Flood Control Structure Along Cabittauran River (Left Bank), Barangay Cabittauran, Sitio Caduyungan 1, Nueva Era, Ilocos NorteDPWH project · contractor St Matthew Gen Contractor & Development Corp
- C3 · Duplicate or Near-Duplicate ProjectsConstruction of Flood Control Structure Along Bongo River, Left Bank, Laoag River Basin Flood Control and Sabo Project, Brgy. Poblacion, Sitio Inging 2, Nueva Era, Ilocos NorteDPWH project · contractor Alpha & Omega Gen Contractor & Development Corp