9 published flags on records linked to Pototan and the LGUs under it. A flag is an automated anomaly that reviewers checked before publishing: a question worth asking, not a finding of wrongdoing.
- C3 · Duplicate or Near-Duplicate ProjectsConstruction of Flood Control Structure Along Jalaur River, Pototan, IloiloDPWH project · contractor A D Pendon Const & Supply Inc Formerly: Adp Const & Supply
- C3 · Duplicate or Near-Duplicate ProjectsConstruction of Flood Control/Slope Protection Along Suage River, Pototan, IloiloDPWH project · contractor Roprim Const Corp Formerly Roprim Const
- C3 · Duplicate or Near-Duplicate ProjectsConstruction of Flood Control Structure/Slope Protection Structure Along Suage River, Pototan, IloiloDPWH project · contractor Roprim Const Corp Formerly Roprim Const
- C1 · Contractor Concentration (Flood Control)A D Pendon Const & Supply Inc Formerly: Adp Const & SupplyContractor (applies to all its work) · contractor A D Pendon Const & Supply Inc Formerly: Adp Const & Supply
- C1 · Contractor Concentration (Flood Control)A D Pendon Const & Supply Inc Formerly: Adp Const & SupplyContractor (applies to all its work) · contractor A D Pendon Const & Supply Inc Formerly: Adp Const & Supply
- C1 · Contractor Concentration (Flood Control)A D Pendon Const & Supply Inc Formerly: Adp Const & SupplyContractor (applies to all its work) · contractor A D Pendon Const & Supply Inc Formerly: Adp Const & Supply
- C1 · Contractor Concentration (Flood Control)F Gurrea Const IncContractor (applies to all its work) · contractor F Gurrea Const Inc
- C1 · Contractor Concentration (Flood Control)Ibc International Builders CorpContractor (applies to all its work) · contractor Ibc International Builders Corp
- C4 · Schedule / Date InconsistenciesConstruction of Flood Mitigation Structure Along Jalaur River, Brgy. Sohoton to Brgy. Patag, Barotac Nuevo, IloiloDPWH project · contractor Early Riser Const / Cmg Jr Builders