8 published flags on records linked to Binongto-an and the LGUs under it. A flag is an automated anomaly that reviewers checked before publishing: a question worth asking, not a finding of wrongdoing.
- C3 · Duplicate or Near-Duplicate ProjectsConstruction of Flood Control Structure Along Binahaan River, Barangay Cahumayhumayan, Tanauan, LeyteDPWH project · contractor Jelm Const Corp
- C1 · Contractor Concentration (Flood Control)Sunwest Inc Formerly: Sunwest Const & Development CorpContractor (applies to all its work) · contractor Sunwest Inc Formerly: Sunwest Const & Development Corp
- C1 · Contractor Concentration (Flood Control)Ezjones Const IncContractor (applies to all its work) · contractor Ezjones Const Inc
- C3 · Duplicate or Near-Duplicate ProjectsConstruction of Flood Control Along Binahaan River, Barangay Cahumayhumayan, Tanauan, LeyteDPWH project · contractor Pablo S Labasbas Const Corp Formerly: Pablos Labasbas Const Corp / Jgo Builders
- C7 · High Concurrent Workload for One ContractorSunwest Inc Formerly: Sunwest Const & Development CorpContractor (applies to all its work) · contractor Sunwest Inc Formerly: Sunwest Const & Development Corp
- C1 · Contractor Concentration (Flood Control)Sunwest Inc Formerly: Sunwest Const & Development CorpContractor (applies to all its work) · contractor Sunwest Inc Formerly: Sunwest Const & Development Corp
- C4 · Schedule / Date InconsistenciesConstruction of Flood Control Structure Along Binahaan River, Barangay Cahumayhumayan, Tanauan, LeyteDPWH project · contractor Jelm Const Corp
- C2 · Awards Very Close to the Budget CeilingConstruction of Flood Control Mitigation Facilities Along Binahaan River, Brgy. Binongtoan Section (Downstream), Sta. 0 + 00 to Sta. 0 + 465, Tanauan, LeyteDPWH project · contractor Sunwest Inc Formerly: Sunwest Const & Development Corp