Buildings and Facilities23KA0114

CONSTRUCTION OF MULTI-PURPOSE BUILDING, BARANGAY HALAPITAN, SAN FERNANDO, BUKIDNON,BARANGAY HALAPITAN, SAN FERNANDO, BUKIDNON 2ND LD

CONSTRUCTION OF MULTI-PURPOSE BUILDING, BARANGAY HALAPITAN, SAN FERNANDO, BUKIDNON,BARANGAY HALAPITAN, SAN FERNANDO, BUKIDNON 2ND LD is a DPWH-tracked public work in Bukidnon 1st DEO, Region X. Reported contract value: ₱7,868,170.25. Status: Reported complete (DPWH). Contractor on record: GREENEXT BUILDERS. Figures trace to dpwh.

Bukidnon 1st DEO, Region X
Region: Region X

Follow the peso

2 of 5 steps linked to this project. Links are automated matches unless marked confirmed.

  1. 1. GAA budget line

    FY2023 · ₱50,000

    Probable match · score 0.85

    DBM GAA source ↗
  2. 2. SARO / NCA release

    No SARO/NCA found for this office and year. DBM publishes releases by agency and office, rarely by project.

  3. 3. PhilGEPS award

    Not found in PhilGEPS by contract ID 23KA0114 or title. The open PhilGEPS mirror does not include every DPWH notice.

  4. 4. DPWH progress + satellite

    100% reported · imagery 2019-12-08 → 2025-08-02

    Same record (DPWH contract ID)

    DPWH Transparency Portal source ↗
  5. 5. COA audit finding

    No COA finding names this project. COA audits DPWH by office each year; project-level findings are only linked when the report names the contract.

Been to this site?

Share a photo of what is there today. Faces and vehicle plates are blurred automatically, all photo metadata except the date and location is removed, and nothing is published until a moderator approves it.

Watch this project

Get a weekly email when this project changes: progress, new linked records or newly published anomaly flags.

Share card: CONSTRUCTION OF MULTI-PURPOSE BUILDING, BARANGAY HALAPITAN, SAN FERNANDO, BUKIDNON,BARANGAY HALAPITAN, SAN FERNANDO, BUKIDNON 2ND LD

Share this page

The card shows the public record facts and a QR code back to this page.

FacebookDownload image

Money Trail

1. Appropriation

Probable match · score 85%

UACS
18001
Amount
₱50,000,000.00 (GAA By-Object, amounts in ₱'000 × 1,000)
Program / description
Construction of Flood Mitigation Structure along Kapalong-Talaingod-Valencia Road (Tigwa River), Barangay Halapitan, San Fernando, Bukidnon
GAA fiscal year
FY2023
DBM GAA source document

2. Allotment

Agency-level releases for FY2023, not tied to this contract

Bukidnon 1st DEO · SARO 16 (₱22,616,681,592.00) · NCA 0 (₱0.00)

3. Procurement & Award

No PhilGEPS award linked in the link table for this contract yet.

Contractor

C

7 projects · ₱28.5M total · 0 flags

4. Implementation

Contract Amount

₱7,868,170.25

Progress

Reported complete (DPWH)

Start Date

February 22, 2023

Target End

November 7, 2023

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.

Connected records

Where this project sits

Place (PSGC)
Region X (Northern Mindanao)BukidnonSan FernandoHalapitan
Storms whose wind field reached it
None on record (IBTrACS tracks).
Hazard exposure
No medium/high hazard on the mapped layers.Details in Hazard context above.Full hazard check →
El Niño outlook (province)
No PAGASA drought or dry flag for this province.El Niño readiness →

Exposure to a storm, hazard or drought outlook is context, not a finding about the project.