Bridges23CE0069

REPLACEMENT OF PERMANENT WEAK BRIDGES - PATOLA BR. (B05032LZ) ALONG GUIMBA - TALUGTUG-UMINGAN RD

REPLACEMENT OF PERMANENT WEAK BRIDGES - PATOLA BR. (B05032LZ) ALONG GUIMBA - TALUGTUG-UMINGAN RD is a DPWH-tracked public work in Nueva Ecija 1st DEO, Region III. Reported contract value: ₱31,416,386.68. Status: Reported complete (DPWH). Contractor on record: D S PAMINTUAN CONST. Figures trace to dpwh.

Nueva Ecija 1st DEO, Region III
Region: Region III

Money Trail

1. Appropriation

Possible match · score 82%

UACS
18001
Amount
₱5,000,000.00 (GAA By-Object, amounts in ₱'000 × 1,000)
Program / description
Construction of Flood Control Structures along Casongsong River, Brgy. Casongsong, Guimba, Nueva Ecija
GAA fiscal year
FY2023
DBM GAA source document

2. Allotment

Office-level release, not tied to this specific contract

SARO SARO-BMB-F-23-0021814

₱1,771,702.00 · FY2023

Released to CALABARZON Region Campus (office-level, not project-specific). This SARO/NCA funds the office's programme; DBM listings do not tie it to this contract.

DBM SARO listing (source)

3. Procurement & Award

No PhilGEPS award linked in the link table for this contract yet.

Contractor

72 projects · ₱1.6B total · 0 flags

4. Implementation

Contract Amount

₱31,416,386.68

Progress

Reported complete (DPWH)

Start Date

February 20, 2023

Target End

April 30, 2024

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.