GAA 2025 SSP25CP0069

CONVERGE. AND SPECIAL SUPPORT PROG. -SUSTAINABLE INFRA. PROJ. ALLEVIATING GAPS (SIPAG) - SIPAG - ACCESS ROADS AND/OR BRIDGES FROM THE NATIONAL ROADDS LEADING TO MAJOR/ STRAT. PUBLIC BLDGS./ FACILITIES - CONST. OF ROAD, PAHSE II SITIO BALIKIRAN, BARANGAY C

CONVERGE. AND SPECIAL SUPPORT PROG. -SUSTAINABLE INFRA. PROJ. ALLEVIATING GAPS (SIPAG) - SIPAG - ACCESS ROADS AND/OR BRIDGES FROM THE NATIONAL ROADDS LEADING TO MAJOR/ STRAT. PUBLIC BLDGS./ FACILITIES - CONST. OF ROAD, PAHSE II SITIO BALIKIRAN, BARANGAY C is a DPWH-tracked public work in Bulacan 3rd DEO, Region III. Reported contract value: ₱142,578,449.07. Status: Past target date (DPWH On-Going). Contractor on record: L R TIQUI BUILDERS INC. Figures trace to dpwh.

Bulacan 3rd DEO, Region III
Region: Region III

Money Trail

1. Appropriation

Possible match · score 81%

UACS
18001
Amount
₱20,000,000.00 (GAA By-Object, amounts in ₱'000 × 1,000)
Program / description
Construction of Flood Control Structure (Check Gate), Barangay Tampok and Barangay Santa Monica, Hagonoy, Bulacan
GAA fiscal year
FY2025
DBM GAA source document

2. Allotment

Office-level release, not tied to this specific contract

SARO SARO-CAR-25-0008445

₱4,870,231.00 · FY2025

Source

3. Procurement & Award

No PhilGEPS award linked in the link table for this contract yet.

Contractor

380 projects · ₱29.1B total · 8 flags

Other projects by this contractor

View all 380 projects →

4. Implementation

Contract Amount

₱142,578,449.07

Progress

Past target date (DPWH On-Going)

Start Date

April 14, 2025

Target End

December 9, 2025