Roads17PI0054

CONSTRUCTION/IMPROVEMENT/REHABILITATION/UPGRADING OF BALICANAO-SALIN FMR, BRGY. SADSADAN, BAUKO, MOUNTAIN PROVINCE

CONSTRUCTION/IMPROVEMENT/REHABILITATION/UPGRADING OF BALICANAO-SALIN FMR, BRGY. SADSADAN, BAUKO, MOUNTAIN PROVINCE is a DPWH-tracked public work in Mountain Province 1st DEO, Cordillera Administrative Region. Reported contract value: ₱2,848,426.83. Status: Reported complete (DPWH). Contractor on record: FJ MIRANDA CONST. Figures trace to dpwh.

Mountain Province 1st DEO, Cordillera Administrative Region
Region: Cordillera Administrative Region

Money Trail

1. Appropriation

No matching GAA line found for this project in the FY2017 GAA. DBM GAA FY2017

2. Allotment

Office-level release, not tied to this specific contract

SARO SARO-ROXII-17-0010461

₱7,894,582.00 · FY2017

Released to Division of South Cotabato (office-level, not project-specific). This SARO/NCA funds the office's programme; DBM listings do not tie it to this contract.

DBM SARO listing (source)

3. Procurement & Award

No PhilGEPS award linked in the link table for this contract yet.

Contractor

B

53 projects · ₱472.3M total · 1 flags

4. Implementation

Contract Amount

₱2,848,426.83

Progress

Reported complete (DPWH)

Start Date

June 29, 2017

Target End

August 4, 2017

5. Audit