Buildings and Facilities17BD0176

CONSTRUCTION OF ONE (1) STOREY TWO (2) CL. UNIQUE WORKSHOP BUILDING, CORDOVA NATIONAL HIGH SCHOOL, AMULUNG, CAGAYAN

CONSTRUCTION OF ONE (1) STOREY TWO (2) CL. UNIQUE WORKSHOP BUILDING, CORDOVA NATIONAL HIGH SCHOOL, AMULUNG, CAGAYAN is a DPWH-tracked public work in Cagayan 3rd DEO, Region II. Reported contract value: ₱5,691,875.78. Status: Reported complete (DPWH). Contractor on record: OML CONST. Figures trace to dpwh.

Cagayan 3rd DEO, Region II
Region: Region II

Satellite images processing — before/after tiles will appear here after the next batch run.

Money Trail

1. Appropriation

Possible match · score 84%

UACS
18001
Amount
₱45,047,000.00 (GAA By-Object, amounts in ₱'000 × 1,000)
Program / description
Construction of Dugayung Flood Control System (Downstream), Sta. 0+306 – Sta. 0+442, Dugayung, Amulung, Cagayan
GAA fiscal year
FY2017
DBM GAA source document

2. Allotment

Office-level release, not tied to this specific contract

SARO SARO-BMB-E-17-0025300

₱5,300,000.00 · FY2017

Source

3. Procurement & Award

4. Implementation

Contract Amount

₱5,691,875.78

Progress

Reported complete (DPWH)

Start Date

December 28, 2017

Target End

May 11, 2018

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.