Buildings and Facilities20CB0059

CONSTRUCTION OF MULTI-PURPOSE BUILDING, BRGY. SABATAN, ORION, BATAAN

CONSTRUCTION OF MULTI-PURPOSE BUILDING, BRGY. SABATAN, ORION, BATAAN is a DPWH-tracked public work in Bataan 2nd DEO, Region III. Reported contract value: ₱4,900,000.00. Status: Reported complete (DPWH). Contractor on record: A T P CONST. Figures trace to dpwh.

Bataan 2nd DEO, Region III
Region: Region III

Satellite images processing — before/after tiles will appear here after the next batch run.

Money Trail

1. Appropriation

Possible match · score 85%

UACS
18001
Amount
₱50,000,000.00 (GAA By-Object, amounts in ₱'000 × 1,000)
Program / description
Construction of Flood Control Structure, Cupang Section, Brgy. Cupang, Balanga, Bataan
GAA fiscal year
FY2020
DBM GAA source document

2. Allotment

Office-level release, not tied to this specific contract

NCA NCA-ROVI-20-0004838

₱6,412,000.00 · FY2020

Released to Tubungan National High School (office-level, not project-specific). This SARO/NCA funds the office's programme; DBM listings do not tie it to this contract.

DBM NCA listing (source)

3. Procurement & Award

4. Implementation

Contract Amount

₱4,900,000.00

Progress

Reported complete (DPWH)

Start Date

October 16, 2020

Target End

January 13, 2021

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.