Flood Control and Drainage23JF0048

CONSTRUCTION OF SHORELINE PROTECTION, BARANGAY PRESIDENT ROXAS, R.T. LIM, ZAMBOANGA SIBUGAY PACKAGE 1

CONSTRUCTION OF SHORELINE PROTECTION, BARANGAY PRESIDENT ROXAS, R.T. LIM, ZAMBOANGA SIBUGAY PACKAGE 1 is a DPWH-tracked public work in Zamboanga Sibugay 2nd DEO, Region IX. Reported contract value: ₱144,650,468.41. Status: Past target date (DPWH On-Going). Contractor on record: ALPHA & OMEGA GEN CONTRACTOR & DEVELOPMENT CORP REVOKED 38958. Figures trace to dpwh.

Zamboanga Sibugay 2nd DEO, Region IX
Region: Region IX

Money Trail

1. Appropriation

Probable match · score 86%

UACS
18001
Amount
₱50,000,000.00 (GAA By-Object, amounts in ₱'000 × 1,000)
Program / description
Construction of Flood Control along Sibuguey River, Barangay Villacastor, Buug, Zamboanga Sibugay Package 3
GAA fiscal year
FY2023
DBM GAA source document

2. Allotment

Office-level release, not tied to this specific contract

SARO SARO-ROV-23-0023800

₱6,342,353.00 · FY2023

Source

3. Procurement & Award

No PhilGEPS award linked in the link table for this contract yet.

Contractor

DPWH ID 38958

57 projects · ₱5.3B total · 0 flags

Other projects by this contractor

View all 57 projects →

4. Implementation

Contract Amount

₱144,650,468.41

Progress

Past target date (DPWH On-Going)

Start Date

August 30, 2023

Target End

February 20, 2025

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.