Roads22BI0031

CONVERGENCE AND SPECIAL SUPPORT PROGRAM (CSSP) CONSTRUCTION/IMPROVEMENT OF ACCESS ROADS LEADING TO DECLARED TOURISM DESTINATION (TOURISM ROAD INFRASTRUCTURE PROGRAM-TRIP) ACCESS ROAD LEADING TO LOWER MAGAT ECOTOURISM PARK

CONVERGENCE AND SPECIAL SUPPORT PROGRAM (CSSP) CONSTRUCTION/IMPROVEMENT OF ACCESS ROADS LEADING TO DECLARED TOURISM DESTINATION (TOURISM ROAD INFRASTRUCTURE PROGRAM-TRIP) ACCESS ROAD LEADING TO LOWER MAGAT ECOTOURISM PARK is a DPWH-tracked public work in Nueva Vizcaya DEO, Region II. Reported contract value: ₱9,611,349.09. Status: Reported complete (DPWH). Contractor on record: E M BAYATAN CONST. Figures trace to dpwh.

Nueva Vizcaya DEO, Region II
Region: Region II

Satellite images processing — before/after tiles will appear here after the next batch run.

Money Trail

1. Appropriation

Possible match · score 83%

UACS
18001
Amount
₱30,000,000.00 (GAA By-Object, amounts in ₱'000 × 1,000)
Program / description
Rehabilitation of Flood Control and Drainage Structures along Magat River, Vista Alegre Section (Phase 5), Sta. 0 + 363.85 - Sta. 0 + 413.85, Sta. 0 + 593.85 - Sta. 0 + 893.85, Bayombong, Nueva Vizcaya
GAA fiscal year
FY2022
DBM GAA source document

2. Allotment

Office-level release, not tied to this specific contract

NCA NCA-BMB-C-22-0005595

₱19,407,042.00 · FY2022

Released to Central Office (NIA) (office-level, not project-specific). This SARO/NCA funds the office's programme; DBM listings do not tie it to this contract.

DBM NCA listing (source)

3. Procurement & Award

No PhilGEPS award linked in the link table for this contract yet.

Contractor

27 projects · ₱275.6M total · 0 flags

Other projects by this contractor

No sat.

CONVERGENCE AND SPECIAL SUPPORT PROGRAM(CSSP)-BASIC INFRASTRUCTURE PROGRAM (BIP)-MULTI-PURPOSE BUILDINGS/FACILITIES TO SUPPORT SOCIAL SERVICES-CONSTRUCTION OF MULTI-PURPOSE BUILDING, BRGY. POBLACION, AMBAGUIO, NUEVA VIZCAYA (MUNICIPAL BUILDING)

Nueva Vizcaya DEO, Region II

2022₱29.7M
Reported complete (DPWH)
No sat.

FLOOD MANAGEMENT PROGRAM CONSTRUCTION/ MAINTENANCE OF FLOOD MITIGATION STRUCTURES AND DRAINAGE SYSTEMCONSTRUCTION OF BENAY RIVER FLOOD CONTROL STRUCTURES, BAGUMBAYAN SECTION, DUPAX DEL SUR, NUEVA VIZCAYA

Nueva Vizcaya 2nd DEO, Region II

2019₱25.0M
Reported complete (DPWH)
No sat.

CONVERGENCE AND SPECIAL SUPPORT PROGRAM CONSTRUCTION/REHABILITATION OF WATER SUPPLY/SEPTAGE AND SEWERAGE/RAIN WATER COLLECTORS WATER SUPPLY SYSTEM CONSTRUCTION OF WATER SYSTEM FOR BAROBBOB MASOC TO RESERVOIR LUYANG, BAYOMBONG, NUEVA

Nueva Vizcaya DEO, Region II

2025₱24.2M
Reported complete (DPWH)
No sat.

CONVERGENCE SPECIAL SUPPORT PROGRAM- CONSTRUCTION/IMPROVEMENT OF ACCESS ROADS LEADING TO DECLARED TOURISM DESTINATIONS (TOURISM ROAD INFRASTRUCTURE PROGRAM-TRIP) ACCESS ROAD LEADING TO LOWER MAGAT ECOTOUR

Nueva Vizcaya DEO, Region II

2023₱20.8M
Reported complete (DPWH)
No sat.

CONST'N OF MULTI-PURPOSE BLDG. AT PUROK 6 BRGY. BUSILAC, BAYOMBONG, NUEVA VIZCAYA

Nueva Vizcaya DEO, Region II

2016₱19.8M
Reported complete (DPWH)
No sat.

LOCAL PROGRAM-LOCAL ROADS AND BRIDGES-LOCAL ROADS-CONSTRUCTION/REPAIR/REHABILITATION/IMPROVEMENT OF VARIOUS INFRASTRUCTURE INCLUDING LOCAL PROJECTS-CONCRETING/IMPROVEMENT OF ROAD IN BARANGAY POBLACION, AMBAGUIO, NUEVA VIZCAYA

Nueva Vizcaya DEO, Region II

2021₱18.7M
Reported complete (DPWH)
View all 27 projects →

4. Implementation

Contract Amount

₱9,611,349.09

Progress

Reported complete (DPWH)

Start Date

February 10, 2022

Target End

July 7, 2022

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.