Roads25BB0002

OO1-ENSURESAFE&RELIABLE NAT'L RDSYS.-ASSET PRESRVAT'NPROG.-REHAB./RECONST./UPGRDNG OF DAMGD PAVD RDS-SECON.RDS-REHAB.OF PAVD RD-MMR-K0554+(-267.50)-K0555+275.50,K0556+205.40- K0557+298.20,K0584+018-584+765.50,K0587+279-K0587+1482, LAL-LO&STA.TERESITA,CAG.

OO1-ENSURESAFE&RELIABLE NAT'L RDSYS.-ASSET PRESRVAT'NPROG.-REHAB./RECONST./UPGRDNG OF DAMGD PAVD RDS-SECON.RDS-REHAB.OF PAVD RD-MMR-K0554+(-267.50)-K0555+275.50,K0556+205.40- K0557+298.20,K0584+018-584+765.50,K0587+279-K0587+1482, LAL-LO&STA.TERESITA,CAG. is a DPWH-tracked public work in Cagayan 1st DEO, Region II. Reported contract value: ₱29,394,798.52. Status: Past target date (DPWH On-Going). Contractor on record: APS CONST. Figures trace to dpwh.

Cagayan 1st DEO, Region II
Region: Region II

Satellite images processing — before/after tiles will appear here after the next batch run.

Money Trail

1. Appropriation

Possible match · score 80%

UACS
18001
Amount
₱50,000,000.00 (GAA By-Object, amounts in ₱'000 × 1,000)
Program / description
Construction of Flood Control Structures Along Paranan River, Baggao, Cagayan
GAA fiscal year
FY2025
DBM GAA source document

2. Allotment

Office-level release, not tied to this specific contract

NCA NCA-ROV-25-0010628

₱151,340,000.00 · FY2025

Released to Division of Camarines Sur (office-level, not project-specific). This SARO/NCA funds the office's programme; DBM listings do not tie it to this contract.

DBM NCA listing (source)

3. Procurement & Award

No PhilGEPS award linked in the link table for this contract yet.

Contractor

C

143 projects · ₱1.5B total · 0 flags

Other projects by this contractor

No sat.

OO1: ENSURE SAFE AND RELIABLE NATIONAL ROAD SYSTEM - BRIDGE PROGRAM - BRIDGE - REPLACEMENT OF PERMANENT WEAK BRIDGES - REPLACEMENT OF WEAK BRIDGE - NADDUNGAN BR. 1 (B02132LZ) ALONG JCT. MAGAPIT CAPISSAYAN ROAD, GATTARAN, CAGAYAN

Cagayan 1st DEO, Region II

2025₱70.2M
Past target date (DPWH On-Going)
No sat.

OO1: ENSURE SAFE AND RELIABLE NATIONAL ROAD SYSTEM - NETWORK DEVELOPMENT - CONSTRUCTION OF BY - PASS AND DIVERSION ROADS - CONSTRUCTION OF CONCRETE ROAD - GATTARAN DIVERSION ROAD (PACKAGE I), CAGAYAN, GATTARAN, CAGAYAN

Cagayan 1st DEO, Region II

2022₱57.3M
Reported complete (DPWH)
No sat.

OO1 - ENSURE SAFE AND RELIABLE NATIONAL ROAD SYSTEM - NETWORK DEVELOPMENT - ROAD WIDENING - SECONDARY ROADS - ROAD WIDENING - DUGO-SN VICENTE RD (MISSION-STA ANA SECT) - K0632 + 324.48 - K0634 + 689, STA. ANA, CAGAYAN

Cagayan 1st DEO, Region II

2025₱49.0M
Past target date (DPWH On-Going)
No sat.

LOCAL PROGRAM - LOCAL ROADS AND BRIDGES - LOCAL ROADS-CONSTRUCTION/REPAIR/REHABILITATION/IMPROVEMENT OF VARIOUS INFRASTRUCTURE INCL. LOCAL PROJECTS-CONSTRUCTION OF CONCRETE ROAD-CONST. OF PATUNUNGAN-PANANACPAN ROAD, BARANGAY PATUNUNGAN, SANTA ANA, CAGAYAN

Cagayan 1st DEO, Region II

2021₱39.0M
Reported complete (DPWH)
No sat.

Construction of Flood Control Structure along Cagayan River, Dugo, Camalaniugan, Cagayan

CAMALANIUGAN (CAGAYAN), CAGAYAN, Region II

2023₱35.3M
Reported complete (DPWH)
No sat.

Construction of Flood Control Structure along Cagayan River, Bulala, Camalaniugan, Cagayan

CAMALANIUGAN (CAGAYAN), CAGAYAN, Region II

2023₱35.3M
Reported complete (DPWH)
View all 143 projects →

4. Implementation

Contract Amount

₱29,394,798.52

Progress

Past target date (DPWH On-Going)

Start Date

June 18, 2025

Target End

November 15, 2025

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.