Roads18ND0064

REHABILITATION/RECONSTRUCTION OF ROADS WITH SLIP, SLOPE COLLAPSE, AND LANDSLIDES ALONG BUTUAN CITY-MALAYBALAY ROAD K1251+330-K1251+345-K1263+779-K1263+815-K1267+794-K1267+831, BUTUAN CITY

REHABILITATION/RECONSTRUCTION OF ROADS WITH SLIP, SLOPE COLLAPSE, AND LANDSLIDES ALONG BUTUAN CITY-MALAYBALAY ROAD K1251+330-K1251+345-K1263+779-K1263+815-K1267+794-K1267+831, BUTUAN CITY is a DPWH-tracked public work in Butuan City DEO, Region XIII. Reported contract value: ₱31,359,991.80. Status: Reported complete (DPWH). Contractor on record: RAMISES CONST. Figures trace to dpwh.

Butuan City DEO, Region XIII
Region: Region XIII

Follow the peso

2 of 5 steps linked to this project, 2 at office level only. Links are automated matches unless marked confirmed.

  1. 1. GAA budget line

    District-office budget line, FY2018 · ₱30,000 (shared by many projects, not this project's own line)

    Possible match · score 0.84

    DBM GAA source ↗
  2. 2. SARO / NCA release

    SARO SARO-ROXIII-18-0000316 · · release to the district office, not itemized per project

    Possible match · score 0.82

    DBM release source ↗
  3. 3. PhilGEPS award

    Not found in PhilGEPS by contract ID 18ND0064 or title. The open PhilGEPS mirror does not include every DPWH notice.

  4. 4. DPWH progress + satellite

    100% reported · imagery 2016-02-06 → 2025-11-12

    Same record (DPWH contract ID)

    DPWH Transparency Portal source ↗
  5. 5. COA audit finding

    CY2019 · other

    Confirmed (exact contract ID) · score 1.00

    COA AAR source ↗

Been to this site?

Share a photo of what is there today. Faces and vehicle plates are blurred automatically, all photo metadata except the date and location is removed, and nothing is published until a moderator approves it.

Watch this project

Get a weekly email when this project changes: progress, new linked records or newly published anomaly flags.

Share card: REHABILITATION/RECONSTRUCTION OF ROADS WITH SLIP, SLOPE COLLAPSE, AND LANDSLIDES ALONG BUTUAN CITY-MALAYBALAY ROAD K1251+330-K1251+345-K1263+779-K1263+815-K1267+794-K1267+831, BUTUAN CITY

Share this page

The card shows the public record facts and a QR code back to this page.

FacebookDownload image

Money Trail

1. Appropriation

Possible match · score 84%

UACS
18001
Amount
₱30,000,000.00 (GAA By-Object, amounts in ₱'000 × 1,000)
Program / description
Improvement of Bank Protection along Agusan River Basin, Amparo Section, Tungao, Butuan City
GAA fiscal year
FY2018
DBM GAA source document

2. Allotment

Office-level release, not tied to this specific contract

SARO SARO-ROXIII-18-0000316

₱0.00 · FY2018

Released to Division of Butuan City (office-level, not project-specific). This SARO/NCA funds the office's programme; DBM listings do not tie it to this contract.

DBM SARO listing (source)

3. Procurement & Award

4. Implementation

Contract Amount

₱31,359,991.80

Progress

Reported complete (DPWH)

Start Date

April 23, 2018

Target End

January 9, 2019

5. Audit

Confirmed (exact contract ID) · 100%

COA observation (CY2019 audit, Observation 12: Contract cost of 184 projects implemented by different DPWH offices were found excessive by the COA Technical Audit Specialists for a total of P431,933,006.20 due to contract costs that exceeded the COA allowable cost. / Table 44 - Breakdown of Contracts Cost Exceeding the Allowable COA Estimates) names Contract ID 18ND0064, p. 191. Excerpt (table columns may run together): "XIII Butuan City DEO For Project ID Nos. 18ND0035, 18ND0045 and 18ND0064 to compensate the amount deficient, the contractor performed an additional length of 8.5 meters. The contractor used crushed fine and coarse aggregates. The programmer used 49km/m weight of Steel Sheet Piles GSP 2 instead of 48 kg/m. It is further noted that"

CY2019 · p.191

Connected records

Where this project sits

Place (PSGC)
Region XIII (Caraga)City of ButuanAmparo
Storms whose wind field reached it
None on record (IBTrACS tracks).
Hazard exposure
No medium/high hazard on the mapped layers.Details in Hazard context above.Full hazard check →
El Niño outlook (province)
No province on record.El Niño readiness →

Exposure to a storm, hazard or drought outlook is context, not a finding about the project.