Roads19GN0100

CONCRETING OF BRGY. AYUNGON FMR, BRGY. AYUNGON, LA CARLOTA CITY, NEGROS OCCIDENTAL

CONCRETING OF BRGY. AYUNGON FMR, BRGY. AYUNGON, LA CARLOTA CITY, NEGROS OCCIDENTAL is a DPWH-tracked public work in Negros Occidental 4th DEO, Negros Island Region. Reported contract value: ₱4,825,748.72. Status: Reported complete (DPWH). Contractor on record: ONE TERRA BUILDERS AND CONST SUPPLY. Figures trace to dpwh.

Negros Occidental 4th DEO, Negros Island Region
Region: Negros Island Region

Follow the peso

1 of 5 steps linked to this project, 1 at office level only. Links are automated matches unless marked confirmed.

  1. 1. GAA budget line

    No GAA line found for this project's office and year. The GAA lists budgets by program and office, not always by project.

  2. 2. SARO / NCA release

    NCA NCA-ROVI-19-0025664 · ₱989,429 · release to the district office, not itemized per project

    Possible match · score 0.82

    DBM release source ↗
  3. 3. PhilGEPS award

    Not found in PhilGEPS by contract ID 19GN0100 or title. The open PhilGEPS mirror does not include every DPWH notice.

  4. 4. DPWH progress + satellite

    100% reported · imagery 2019-06-13 → 2025-09-04

    Same record (DPWH contract ID)

    DPWH Transparency Portal source ↗
  5. 5. COA audit finding

    No COA finding names this project. COA audits DPWH by office each year; project-level findings are only linked when the report names the contract.

Been to this site?

Share a photo of what is there today. Faces and vehicle plates are blurred automatically, all photo metadata except the date and location is removed, and nothing is published until a moderator approves it.

Watch this project

Get a weekly email when this project changes: progress, new linked records or newly published anomaly flags.

Share card: CONCRETING OF BRGY. AYUNGON FMR, BRGY. AYUNGON, LA CARLOTA CITY, NEGROS OCCIDENTAL

Share this page

The card shows the public record facts and a QR code back to this page.

FacebookDownload image

Money Trail

1. Appropriation

No matching GAA line found for this project in the FY2019 GAA. DBM GAA FY2019

2. Allotment

Office-level release, not tied to this specific contract

NCA NCA-ROVI-19-0025664

₱989,429.00 · FY2019

Released to Negros Occidental National Industrial (office-level, not project-specific). This SARO/NCA funds the office's programme; DBM listings do not tie it to this contract.

DBM NCA listing (source)

3. Procurement & Award

No PhilGEPS award linked in the link table for this contract yet.

Contractor

A

86 projects · ₱664.8M total · 0 flags

Other projects by this contractor

No sat.

NETWORK DEVELOPMENT - ROAD WIDENING - TERTIARY ROADS - JCT. PONTEVEDRA - LA CASTELLANA ROAD - K0046+000 - K0047+500

Negros Occidental 4th DEO, Negros Island Region

2024₱53.4M
Reported complete (100% progress, DPWH status On-Going)
No sat.

NETWORK DEVELOPMENT - OFF-CARRIAGEWAY IMPROVEMENT - TERTIARY ROADS - JCT. SAN ENRIQUE - PONTEVEDRA BY-PASS ROAD - K0042+600 - K0045+862, K0045+920 - K0045+962

Negros Occidental 4th DEO, Negros Island Region

2024₱30.6M
Reported complete (100% progress, DPWH status On-Going)
No sat.

REHABILITATION RECONSTRUCTION UPGRADING OF DAMAGED PAVED ROADS - TERTIARY ROADS - JCT. PONTEVEDRA-LA CASTELLANA ROAD, K0045+(-975) -K0045+436, PONTEVEDRA, NEGROS OCCIDENTAL

Negros Occidental 4th DEO, Negros Island Region

2020₱26.1M
Reported complete (DPWH)
No sat.

NETWORK DEVELOPMENT - OFF-CARRIAGEWAY IMPROVEMENT - TERTIARY ROADS - JCT. SAN ENRIQUE - PONTEVEDRA BY-PASS ROAD - K0040+(-664) - K0040+575, K0040+585 - K0041+230, K0041+272 - K0042+600

Negros Occidental 4th DEO, Negros Island Region

2025₱25.2M
Past target date (DPWH On-Going)
No sat.

CONSTRUCTION OF REINFORCED CONCRETE DECK GIRDER (RCDG) BRIDGE INCLUDING APPROACHES AND SIDE SLOPE PROTECTION AT BRGY. CANROMA TO SITIO SUA TRINIDAD ROAD, BRGY. DON SALVADOR BENEDICTO, PONTEVEDRA, NEGROS OCCIDENTAL

Negros Occidental 4th DEO, Negros Island Region

2023₱24.7M
Reported complete (DPWH)
No sat.

RECONSTRUCTION TO CONCRETE PAVEMENT - JCT. PONTEVEDRA - LA CASTELLANA ROAD, K0045+436 - K0046+545, PONTEVEDRA, NEGROS OCCIDENTAL

Negros Occidental 4th DEO, Negros Island Region

2021₱21.7M
Reported complete (DPWH)
View all 86 projects →

4. Implementation

Contract Amount

₱4,825,748.72

Progress

Reported complete (DPWH)

Start Date

October 10, 2019

Target End

November 24, 2019

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.

Connected records

Where this project sits

Place (PSGC)
Negros Island Region (NIR)Negros OccidentalCity of La Carlota
Storms whose wind field reached it
None on record (IBTrACS tracks).
Hazard exposure
No medium/high hazard on the mapped layers.Details in Hazard context above.Full hazard check →
El Niño outlook (province)
No PAGASA drought or dry flag for this province.El Niño readiness →

Exposure to a storm, hazard or drought outlook is context, not a finding about the project.