Bridges18IC0021

WIDENING OF PERMANENT BRIDGES, CANDAHUG BRIDGE (B00052LT) ALONG GOVERNMENT CENTER ROAD NETWORK (S00047LT), PALO, LEYTE

WIDENING OF PERMANENT BRIDGES, CANDAHUG BRIDGE (B00052LT) ALONG GOVERNMENT CENTER ROAD NETWORK (S00047LT), PALO, LEYTE is a DPWH-tracked public work in Leyte 1st DEO, Region VIII. Reported contract value: ₱14,819,893.38. Status: Reported complete (DPWH). Contractor on record: MWJ CONST. Figures trace to dpwh.

Leyte 1st DEO, Region VIII
Region: Region VIII

Money Trail

1. Appropriation

Possible match · score 81%

UACS
18001
Amount
₱25,000,000.00 (GAA By-Object, amounts in ₱'000 × 1,000)
Program / description
Construction Flood Control along Sambulawan River, Brgy. Guindapunan, Palo, Leyte
GAA fiscal year
FY2018
DBM GAA source document

2. Allotment

Agency-level releases for FY2018, not tied to this contract

Leyte 1st DEO · SARO 1,489 (₱126,676,811,675.00) · NCA 1,617 (₱426,584,627,343.00)

3. Procurement & Award

4. Implementation

Contract Amount

₱14,819,893.38

Progress

Reported complete (DPWH)

Start Date

March 1, 2018

Target End

September 27, 2018

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.