Buildings and Facilities24BD0046

BASIC INFRASTRUCTURE PROGRAM (BIP) MULTI-PURPOSE BUILDINGS/FACILITIES TO SUPPORT SOCIAL SERVICES - CONSTRUCTION OF MULTI-PURPOSE BUILDING AT BARANGAY GORAN, AMULUNG, CAGAYAN

BASIC INFRASTRUCTURE PROGRAM (BIP) MULTI-PURPOSE BUILDINGS/FACILITIES TO SUPPORT SOCIAL SERVICES - CONSTRUCTION OF MULTI-PURPOSE BUILDING AT BARANGAY GORAN, AMULUNG, CAGAYAN is a DPWH-tracked public work in Cagayan 3rd DEO, Region II. Reported contract value: ₱4,929,414.29. Status: Reported complete (100% progress, DPWH status On-Going). Contractor on record: 5MJ'S CONST. Figures trace to dpwh.

Cagayan 3rd DEO, Region II
Region: Region II

Money Trail

1. Appropriation

Possible match · score 84%

UACS
18001
Amount
₱20,000,000.00 (GAA By-Object, amounts in ₱'000 × 1,000)
Program / description
Construction of Cagayan River Flood Management Projects, Centro, Amulung, Cagayan
GAA fiscal year
FY2024
DBM GAA source document

2. Allotment

Office-level release, not tied to this specific contract

NCA NCA-ROIII-24-0005899

₱136,257,850.00 · FY2024

Released to Cagayan 3rd DEO (office-level, not project-specific). This SARO/NCA funds the office's programme; DBM listings do not tie it to this contract.

DBM NCA listing (source)

3. Procurement & Award

No PhilGEPS award linked in the link table for this contract yet.

Contractor

46 projects · ₱152.5M total · 0 flags

Other projects by this contractor

No sat.

CONSTRUCTION OF 2-STOREY 6-CLASSROOM SCHOOL BUILDING (PHASE I) IN SITIO DAMORTIS, SAMPAGUITA ELEMENTARY SCHOOL, BARANGAY SAMPAGUITA, SOLANA, CAGAYAN

Cagayan 3rd DEO, Region II

2024₱9.9M
Reported complete (100% progress, DPWH status On-Going)
No sat.

SUSTAINABLE INFRASTRUCTURE PROJECTS ALLEVIATING GAPS (SIPAG) - MULTI-PURPOSE BUILDINGS/FACILITIES TO SUPPORT SOCIAL SERVICES - CONSTRUCTION OF MULTI-PURPOSE BUILDING AT BARANGAY DUGAYUNG, AMULUNG, CAGAYAN

Cagayan 3rd DEO, Region II

2022₱6.9M
Reported complete (DPWH)
No sat.

SUSTAINABLE INFRASTRUCTURE PROJECTS ALLEVIATING GAPS (SIPAG) - FLOOD MITIGATION STRUCTURE PROTECTING MAJOR/STRATEGIC PUBLIC BUILDINGS/FACILITIES - REHABILITATION OF DRAINAGE, BARANGAY AJAT, IGUIG, CAGAYAN - PHASE II

Cagayan 3rd DEO, Region II

2025₱5.3M
Past target date (DPWH On-Going)
No sat.

BASIC INFRASTRUCTURE PROGRAM (BIP) - ACCESS ROADS AND/OR BRIDGES FROM THE NATIONAL ROAD/S LEADING TO MAJOR/ STRATEGIC PUBLIC BUILDINGS/ FACILITIES - CONSTRUCTION OF LOCAL ROAD, SAN ISIDRO, IGUIG, CAGAYAN

Cagayan 3rd DEO, Region II

2024₱4.9M
Reported complete (DPWH)
No sat.

BASIC INFRASTRUCTURE PROGRAM (BIP) - MULTI-PURPOSE BUILDINGS/FACILITIES TO SUPPORT SOCIAL SERVICES - CONSTRUCTION OF MULTI-PURPOSE BUILDING, BARANGAY ALITUNGTUNG, AMULUNG, CAGAYAN

Cagayan 3rd DEO, Region II

2025₱4.9M
Past target date (DPWH On-Going)
No sat.

BASIC INFRASTRUCTURE PROGRAM (BIP) - MULTI-PURPOSE BUILDINGS/FACILITIES TO SUPPORT SOCIAL SERVICES - CONSTRUCTION OF MULTI-PURPOSE BUILDING (SPORTS GYMNASIUM), BARANGAY MINANGA SUR, IGUIG, CAGAYAN

Cagayan 3rd DEO, Region II

2025₱4.9M
Past target date (DPWH On-Going)
View all 46 projects →

4. Implementation

Contract Amount

₱4,929,414.29

Progress

Reported complete (100% progress, DPWH status On-Going)

Start Date

May 15, 2024

Target End

January 9, 2025

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.