Roads21II0019

ROAD WIDENING, TERTIARY ROADS, RAWIS-CATUBIG RD, K0799+234 - K0799+298, K0799+322 - K0799+773.5, 2ND DISTRICT, NORTHERN SAMAR

ROAD WIDENING, TERTIARY ROADS, RAWIS-CATUBIG RD, K0799+234 - K0799+298, K0799+322 - K0799+773.5, 2ND DISTRICT, NORTHERN SAMAR is a DPWH-tracked public work in Northern Samar 2nd DEO, Region VIII. Reported contract value: ₱14,187,716.51. Status: Reported complete (DPWH). Contractor on record: AJADESTIAN CORP. Figures trace to dpwh.

Northern Samar 2nd DEO, Region VIII
Region: Region VIII

Follow the peso

1 of 5 steps linked to this project, 2 at office level only. Links are automated matches unless marked confirmed.

  1. 1. GAA budget line

    District-office budget line, FY2021 · ₱10,000 (shared by many projects, not this project's own line)

    Possible match · score 0.84

    DBM GAA source ↗
  2. 2. SARO / NCA release

    NCA NCA-ROIVA-21-0008181 · ₱407,327,000 · release to the district office, not itemized per project

    Possible match · score 0.62

    DBM release source ↗
  3. 3. PhilGEPS award

    Not found in PhilGEPS by contract ID 21II0019 or title. The open PhilGEPS mirror does not include every DPWH notice.

  4. 4. DPWH progress + satellite

    100% reported · imagery 2015-10-13 → 2015-10-13

    Same record (DPWH contract ID)

    DPWH Transparency Portal source ↗
  5. 5. COA audit finding

    No COA finding names this project. COA audits DPWH by office each year; project-level findings are only linked when the report names the contract.

Unit-cost benchmark · Road, cost per km (widening)

₱27,522,243 per km= 0.8x the Region VIII median (n=337)

Contract cost ₱14,187,717 ÷ 0.516 km read from the DPWH title (“K0799+234 - K0799+298; K0799+322 - K0799+773.5”; K-post / station range length). National percentile: 26. Higher unit cost can have legitimate causes (terrain, design, scope not stated in the title); this is a comparison, not a finding. Methodology

Been to this site?

Share a photo of what is there today. Faces and vehicle plates are blurred automatically, all photo metadata except the date and location is removed, and nothing is published until a moderator approves it.

Watch this project

Get a weekly email when this project changes: progress, new linked records or newly published anomaly flags.

Share card: ROAD WIDENING, TERTIARY ROADS, RAWIS-CATUBIG RD, K0799+234 - K0799+298, K0799+322 - K0799+773.5, 2ND DISTRICT, NORTHERN SAMAR

Share this page

The card shows the public record facts and a QR code back to this page.

FacebookDownload image

Money Trail

1. Appropriation

Possible match · score 84%

UACS
18001
Amount
₱10,000,000.00 (GAA By-Object, amounts in ₱'000 × 1,000)
Program / description
Construction of Flood Control Structure, Barangay Cadac-an, Gamay, Northern Samar
GAA fiscal year
FY2021
DBM GAA source document

2. Allotment

Office-level release, not tied to this specific contract

NCA NCA-ROIVA-21-0008181

₱407,327,000.00 · FY2021

Released to Batangas 2nd District Engineering Office (office-level, not project-specific). This SARO/NCA funds the office's programme; DBM listings do not tie it to this contract.

DBM NCA listing (source)

3. Procurement & Award

4. Implementation

Contract Amount

₱14,187,716.51

Progress

Reported complete (DPWH)

Start Date

March 3, 2021

Target End

June 30, 2021

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.

Connected records

Where this project sits

Place (PSGC)
Region VIII (Eastern Visayas)Northern SamarLaoangOleras
Storms whose wind field reached it
None on record (IBTrACS tracks).
Hazard exposure
Flood (100-yr rain)Details in Hazard context above.Full hazard check →
El Niño outlook (province)
No PAGASA drought or dry flag for this province.El Niño readiness →

Exposure to a storm, hazard or drought outlook is context, not a finding about the project.