Flood Control and Drainage16AA0212

CONST./REHAB OF FLOOD MIT FACI ALONG MAJ RIV & PRINC RIV, BACARRA-VINTAR RIV (BISLAK RIVER) DIPILAT

CONST./REHAB OF FLOOD MIT FACI ALONG MAJ RIV & PRINC RIV, BACARRA-VINTAR RIV (BISLAK RIVER) DIPILAT is a DPWH-tracked public work in Ilocos Norte 1st DEO, Region I. Reported contract value: ₱4,010,217.58. Status: Reported complete (DPWH). Contractor on record: REMAR CONST. Figures trace to dpwh.

Ilocos Norte 1st DEO, Region I
Region: Region I

Satellite images processing — before/after tiles will appear here after the next batch run.

Money Trail

1. Appropriation

GAA FY2016 not yet loaded (source: DBM GAA)

2. Allotment

No SARO/NCA release rows linked to this project yet. See DBM release listings.

3. Procurement & Award

4. Implementation

Contract Amount

₱4,010,217.58

Progress

Reported complete (DPWH)

Start Date

December 2, 2016

Target End

February 27, 2017

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.