GAA 2022 CSSP22DF0206

CONVERGENCE AND SPECIAL SUPPORT PROGRAMSUSTAINABLE INFRASTRUCTURE PROJECTS ALLEVIATING GAPS (SIPAG)SIPAG - MULTI-PURPOSE BUILDINGS/ FACILITIES TO SUPPORT SOCIAL SERVICESCONSTRUCTION OF MULTI-PURPOSE BUILDING, SENIOR HIGH SCHOOL, STA. CLARA, GENERAL

CONVERGENCE AND SPECIAL SUPPORT PROGRAMSUSTAINABLE INFRASTRUCTURE PROJECTS ALLEVIATING GAPS (SIPAG)SIPAG - MULTI-PURPOSE BUILDINGS/ FACILITIES TO SUPPORT SOCIAL SERVICESCONSTRUCTION OF MULTI-PURPOSE BUILDING, SENIOR HIGH SCHOOL, STA. CLARA, GENERAL is a DPWH-tracked public work in Cavite 1st DEO, Region IV-A. Reported contract value: ₱9,800,000.00. Status: Reported complete (100% progress, DPWH status On-Going). Contractor on record: SIAMO YESHA CONST CORP. Figures trace to dpwh.

Cavite 1st DEO, Region IV-A
Region: Region IV-A

Money Trail

1. Appropriation

Possible match · score 79%

UACS
18001
Amount
₱50,000,000.00 (GAA By-Object, amounts in ₱'000 × 1,000)
Program / description
Construction of Flood Control Structure along River in Brgy. Palico 4, Imus City, Cavite
GAA fiscal year
FY2022
DBM GAA source document

2. Allotment

Office-level release, not tied to this specific contract

NCA NCA-ROIII-22-0012874

₱4,197,400.00 · FY2022

Source

3. Procurement & Award

No PhilGEPS award linked in the link table for this contract yet.

Contractor

8 projects · ₱88.4M total · 0 flags

Other projects by this contractor

No sat.

LOCAL PROGRAM NATIONAL BUILDING PROGRAMBUILDINGS AND OTHER STRUCTURESMULTIPURPOSE / FACILITIESCONSTRUCTION OF MULTI-PURPOSE BUILDING, DEPARTMENT OF EDUCATION OFFICE, BARANGAY STA. CLARA, GENERAL TRIAS CITY, CAVITE

Cavite 1st DEO, Region IV-A

2022₱19.6M
Reported complete (DPWH)
No sat.

LOCAL PROGRAMNATIONAL BUILDING PROGRAMBUILDINGS AND OTHER STRUCTURESMULTIPURPOSE / FACILITIESCONSTRUCTION OF MULTI-PURPOSE BUILDING, DIVISION OF GENERAL TRIAS CITY, DEPARTMENT OF EDUCATION OFFICE, BARANGAY STA. CLARA, GENERAL TRIAS CITY, CAVITE

Cavite 1st DEO, Region IV-A

2022₱19.6M
Reported complete (DPWH)
No sat.

CONVERGENCE AND SPECIAL SUPPORT PROGRAMBASIC INFRASTRUCTURE PROGRAM (BIP)BIP - MULTI-PURPOSE BUILDINGS/ FACILITIES TO SUPPORT SOCIAL SERVICESCONSTRUCTION OF MULTI-PURPOSE BUILDING, BARANGAY PASONG CAMACHILE II, GENERAL TRIAS CITY, CAVITE

Cavite 1st DEO, Region IV-A

2022₱9.9M
Reported complete (DPWH)
No sat.

CONVERGENCE AND SPECIAL SUPPORT PROGRAMSUSTAINABLE INFRASTRUCTURE PROJECTS ALLEVIATING GAPS (SIPAG)SIPAG - MULTI-PURPOSE BUILDINGS/ FACILITIES TO SUPPORT SOCIAL SERVICESCONSTRUCTION OF MULTI-PURPOSE BUILDING (DIALYSIS CENTER), SAN FRANCISCO, GENERAL

Cavite 1st DEO, Region IV-A

2022₱9.8M
Reported complete (DPWH)
No sat.

LOCAL PROGRAMNATIONAL BUILDING PROGRAMBUILDINGS AND OTHER STRUCTURESMULTIPURPOSE / FACILITIESCONSTRUCTION OF PUBLIC HEALTH FACILITIES (DIALYSIS CENTER), BARANGAY MANGGAHAN, GENERAL TRIAS CITY, CAVITE

Cavite 1st DEO, Region IV-A

2022₱9.8M
Reported complete (DPWH)
No sat.

CONVERGENCE AND SPECIAL SUPPORT PROGRAMBASIC INFRASTRUCTURE PROGRAM (BIP)BIP - MULTI-PURPOSE BUILDINGS/ FACILITIES TO SUPPORT SOCIAL SERVICESCONSTRUCTION OF MULTI-PURPOSE BUILDING, BRGY. SAN FRANCISCO, GENERAL TRIAS CITY, CAVITE

Cavite 1st DEO, Region IV-A

2022₱5.0M
Reported complete (DPWH)
View all 8 projects →

4. Implementation

Contract Amount

₱9,800,000.00

Progress

Reported complete (100% progress, DPWH status On-Going)

Start Date

March 29, 2022

Target End

April 27, 2023

5. Audit