Buildings and Facilities25KE0029

CONSTRUCTION/COMPLETION OF MULTI-PURPOSE BUILDING (COVERED COURT) BVARANGAY CATIBAC,CATARMAN,CAMIGUIN

CONSTRUCTION/COMPLETION OF MULTI-PURPOSE BUILDING (COVERED COURT) BVARANGAY CATIBAC,CATARMAN,CAMIGUIN is a DPWH-tracked public work in Camiguin DEO, Region X. Reported contract value: ₱4,896,000.00. Status: Reported complete (100% progress, DPWH status On-Going). Contractor on record: FNTC CONST. Figures trace to dpwh.

Camiguin DEO, Region X
Region: Region X

Follow the peso

1 of 5 steps linked to this project, 2 at office level only. Links are automated matches unless marked confirmed.

  1. 1. GAA budget line

    District-office budget line, FY2025 · ₱45,390 (shared by many projects, not this project's own line)

    Possible match · score 0.72

    DBM GAA source ↗
  2. 2. SARO / NCA release

    NCA NCA-ROV-25-0007917 · ₱6,321,094 · release to the district office, not itemized per project

    Possible match · score 0.69

    DBM release source ↗
  3. 3. PhilGEPS award

    Not found in PhilGEPS by contract ID 25KE0029 or title. The open PhilGEPS mirror does not include every DPWH notice.

  4. 4. DPWH progress + satellite

    100% reported · imagery 2016-04-05 → 2016-04-05

    Same record (DPWH contract ID)

    DPWH Transparency Portal source ↗
  5. 5. COA audit finding

    No COA finding names this project. COA audits DPWH by office each year; project-level findings are only linked when the report names the contract.

Been to this site?

Share a photo of what is there today. Faces and vehicle plates are blurred automatically, all photo metadata except the date and location is removed, and nothing is published until a moderator approves it.

Watch this project

Get a weekly email when this project changes: progress, new linked records or newly published anomaly flags.

Share card: CONSTRUCTION/COMPLETION OF MULTI-PURPOSE BUILDING (COVERED COURT) BVARANGAY CATIBAC,CATARMAN,CAMIGUIN

Share this page

The card shows the public record facts and a QR code back to this page.

FacebookDownload image

Money Trail

1. Appropriation

Possible match · score 72%

UACS
18001
Amount
₱45,390,000.00 (GAA By-Object, amounts in ₱'000 × 1,000)
Program / description
Construction of Flood Mitigation Structure along Tagas Bridge, Jct. Nato-Sabang, Camarines Sur
GAA fiscal year
FY2025
DBM GAA source document

2. Allotment

Office-level release, not tied to this specific contract

NCA NCA-ROV-25-0007917

₱6,321,094.00 · FY2025

Released to Camiguin DEO (office-level, not project-specific). This SARO/NCA funds the office's programme; DBM listings do not tie it to this contract.

DBM NCA listing (source)

3. Procurement & Award

4. Implementation

Contract Amount

₱4,896,000.00

Progress

Reported complete (100% progress, DPWH status On-Going)

Start Date

February 5, 2025

Target End

April 20, 2025

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.

Connected records

Where this project sits

Place (PSGC)
Region X (Northern Mindanao)CamiguinCatarmanCatibac
Storms whose wind field reached it
None on record (IBTrACS tracks).
Hazard exposure
Flood (100-yr rain)Storm surgeDetails in Hazard context above.Full hazard check →
El Niño outlook (province)
No PAGASA drought or dry flag for this province.El Niño readiness →

Exposure to a storm, hazard or drought outlook is context, not a finding about the project.