Bridges20OD0181

CONSTRUCTION OF BRIDGE BOUNDARY OF CIUDAD GRANDE, VALENZUELA-MEYCAUAYAN BOUNDARY, BRGY. LINGUNAN, VALENZUELA CITY

CONSTRUCTION OF BRIDGE BOUNDARY OF CIUDAD GRANDE, VALENZUELA-MEYCAUAYAN BOUNDARY, BRGY. LINGUNAN, VALENZUELA CITY is a DPWH-tracked public work in Metro Manila 3rd DEO, National Capital Region. Reported contract value: ₱17,107,304.77. Status: Reported complete (DPWH). Contractor on record: CHRIZMARIE BUILDERS AND CONST SUPPLY. Figures trace to dpwh.

Metro Manila 3rd DEO, National Capital Region
Region: National Capital Region

Money Trail

1. Appropriation

Probable match · score 86%

UACS
18001
Amount
₱10,000,000.00 (GAA By-Object, amounts in ₱'000 × 1,000)
Program / description
Construction of Flood Control Wall along Creeks in Brgy. Maysan, Valenzuela City
GAA fiscal year
FY2020
DBM GAA source document

2. Allotment

Office-level release, not tied to this specific contract

SARO SARO-BMB-B-20-0000649

₱0.00 · FY2020

Released to National Center for Mental Health (office-level, not project-specific). This SARO/NCA funds the office's programme; DBM listings do not tie it to this contract.

DBM SARO listing (source)

3. Procurement & Award

No PhilGEPS award linked in the link table for this contract yet.

Contractor

C

71 projects · ₱1.9B total · 0 flags

Other projects by this contractor

No sat.

CLUSTER 15: 1. SIPAG - ACCESS ROADS AND/OR BRIDGES FROM THE NATIONAL ROAD/S LEADING TO MAJOR/STRATEGIC PUBLIC BUILDINGS/FACILITIES - CONSTRUCTION OF ROAD, BASEY - MAYDOLONG, EASTERN SAMAR; 2. SIPAG - ACCESS ROADS AND/OR BRIDGES FROM THE NATIONAL ROAD/S LE

Region VIII, Region VIII

2023₱247.5M
Past target date (DPWH On-Going)
No sat.

SUSTAINABLE INFRASTRUCTURE PROJECTS ALLEVIATING GAPS (SIPAG) - ACCESS ROADS AND/OR BRIDGES FROM THE NATIONAL ROAD/S LEADING TO MAJOR/STRATEGIC PUBLIC BUILDINGS/FACILITIES - CONSTRUCTION OF ROAD, SITIO KALAWIT - BARANGAY CADIAN, ORAS, EATERN SAMAR

Region VIII, Region VIII

2024₱168.8M
Past target date (DPWH On-Going)
No sat.

SIPAG - ACCESS ROADS AND/OR BRIDGES FROM THE NATIONAL ROADS LEADING TO MAJOR/STRATEGIC PUBLIC BUILDINGS/FACILITIES - REHABILITATION OF MAYDOLONG - BASEY ROAD, EASTERN SAMAR

Region VIII, Region VIII

2025₱158.1M
Past target date (DPWH On-Going)
No sat.

ROAD WIDENING SECONDARY ROADS JCT. BUENAVISTA - LAWAAN - MARABUT RD (S00147SM), K0954+622 - K0955+000, K0955+700 - K0957+600, K0959+594 - K0960+624

Eastern Samar DEO, Region VIII

2025₱133.7M
Past target date (DPWH On-Going)
No sat.

SIPAG - ACCESS ROADS AND/OR BRIDGES FROM THE NATIONAL ROAD/S LEADING TO MAJOR/STRATEGIC PUBLIC BUILDINGS/FACILITIES - CONSTRUCTION OF ROAD PHASE II, BRGY. LUMATOD - DANAO, TAFT, EASTERN SAMAR

Region VIII, Region VIII

2024₱96.4M
Past target date (DPWH On-Going)
No sat.

SIPAG - ACCESS ROADS AND/OR BRIDGES FROM THE NATIONAL ROAD/S LEADING TO MAJOR/STRATEGIC PUBLIC BUILDINGS/FACILITIES - CONSTRUCTION OF ROAD PHASE II, BRGY. POLANGI - GAYAM, TAFT, EASTERN SAMAR LD

Region VIII, Region VIII

2024₱96.4M
Past target date (DPWH On-Going)
View all 71 projects →

4. Implementation

Contract Amount

₱17,107,304.77

Progress

Reported complete (DPWH)

Start Date

July 10, 2020

Target End

February 4, 2021

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.