Roads23C00081

NETWORK DEVELOPMENT PROGRAM-CONSTRUCTION OF BYPASS AND DIVERSION ROADS-LUBAO-GUAGUA-MINALIN-STO. TOMAS ROAD (LUBAO-GUAGUA SECTION), PACKAGE 8, PROVINCE OF PAMPANGA

NETWORK DEVELOPMENT PROGRAM-CONSTRUCTION OF BYPASS AND DIVERSION ROADS-LUBAO-GUAGUA-MINALIN-STO. TOMAS ROAD (LUBAO-GUAGUA SECTION), PACKAGE 8, PROVINCE OF PAMPANGA is a DPWH-tracked public work in Region III, Region III. Reported contract value: ₱121,589,452.65. Status: Reported complete (DPWH). Contractor on record: C. Figures trace to dpwh.

Region III, Region III
Region: Region III

Money Trail

1. Appropriation

No matching GAA line found for this project in the FY2023 GAA. DBM GAA FY2023

2. Allotment

No matching SARO/NCA release found for this project. Source: DBM SARO/NCA listings.

3. Procurement & Award

No PhilGEPS award linked in the link table for this contract yet.

Contractor

B

231 projects · ₱6.0B total · 0 flags

4. Implementation

Contract Amount

₱121,589,452.65

Progress

Reported complete (DPWH)

Start Date

May 1, 2023

Target End

July 21, 2024

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.