Buildings and Facilities24H00142

CONSTRUCTION OF NEW SUPER HEALTH CENTERS/RHU - SAN ISIDRO SUPER HEALTH CENTER, BOHOL

CONSTRUCTION OF NEW SUPER HEALTH CENTERS/RHU - SAN ISIDRO SUPER HEALTH CENTER, BOHOL is a DPWH-tracked public work in Region VII, Region VII. Reported contract value: ₱11,933,000.00. Status: Reported complete (100% progress, DPWH status On-Going). Contractor on record: M M SUAREZ CONST. Figures trace to dpwh.

Region VII, Region VII
Region: Region VII

Money Trail

1. Appropriation

No GAA appropriation line matched for this project at current confidence thresholds.

2. Allotment

No SARO/NCA release rows linked to this project yet. See DBM release listings.

3. Procurement & Award

4. Implementation

Contract Amount

₱11,933,000.00

Progress

Reported complete (100% progress, DPWH status On-Going)

Start Date

October 4, 2024

Target End

March 31, 2025

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.