Roads19HB0079

CONCRETING OF BARANGAY ROAD, PUROK 2 ILAOD BRGY. LICO LICO, SEVILLA, BOHOL STA.0+000-STA.0+075

CONCRETING OF BARANGAY ROAD, PUROK 2 ILAOD BRGY. LICO LICO, SEVILLA, BOHOL STA.0+000-STA.0+075 is a DPWH-tracked public work in Bohol 3rd DEO, Region VII. Reported contract value: ₱940,168.00. Status: Reported complete (DPWH). Contractor on record: CLAVITE CONST AND SUPPLY. Figures trace to dpwh.

Bohol 3rd DEO, Region VII
Region: Region VII

Follow the peso

1 of 5 steps linked to this project, 1 at office level only. Links are automated matches unless marked confirmed.

  1. 1. GAA budget line

    No GAA line found for this project's office and year. The GAA lists budgets by program and office, not always by project.

  2. 2. SARO / NCA release

    NCA NCA-ROVII-19-0011352 · ₱9,308,000 · release to the district office, not itemized per project

    Possible match · score 0.79

    DBM release source ↗
  3. 3. PhilGEPS award

    Not found in PhilGEPS by contract ID 19HB0079 or title. The open PhilGEPS mirror does not include every DPWH notice.

  4. 4. DPWH progress + satellite

    100% reported · imagery 2012-11-28 → 2021-07-29

    Same record (DPWH contract ID)

    DPWH Transparency Portal source ↗
  5. 5. COA audit finding

    No COA finding names this project. COA audits DPWH by office each year; project-level findings are only linked when the report names the contract.

Been to this site?

Share a photo of what is there today. Faces and vehicle plates are blurred automatically, all photo metadata except the date and location is removed, and nothing is published until a moderator approves it.

Watch this project

Get a weekly email when this project changes: progress, new linked records or newly published anomaly flags.

Share card: CONCRETING OF BARANGAY ROAD, PUROK 2 ILAOD BRGY. LICO LICO, SEVILLA, BOHOL STA.0+000-STA.0+075

Share this page

The card shows the public record facts and a QR code back to this page.

FacebookDownload image

Money Trail

1. Appropriation

No matching GAA line found for this project in the FY2019 GAA. DBM GAA FY2019

2. Allotment

Office-level release, not tied to this specific contract

NCA NCA-ROVII-19-0011352

₱9,308,000.00 · FY2019

Released to Sikatuna National Agricultural High Sch (office-level, not project-specific). This SARO/NCA funds the office's programme; DBM listings do not tie it to this contract.

DBM NCA listing (source)

3. Procurement & Award

No PhilGEPS award linked in the link table for this contract yet.

Contractor

A

93 projects · ₱442.3M total · 0 flags

Other projects by this contractor

No sat.

CONVERGENCE AND SPECIAL SUPPORT PROGRAM - BASIC INFRASTRUCTURE PROGRAM (BIP) - ACCESS ROADS AND/OR BRIDGES FROM THE NATIONAL ROAD/S LEADING TO MAJOR/STRATEGIC PUBLIC BUILDINGS/FACILITIES - CONSTRUCTION OF ROADS, CARMEN, BOHOL, SEC. 1 : STA. 0+000 - STA. 0

Bohol 3rd DEO, Region VII

2024₱34.6M
Reported complete (DPWH)
No sat.

CONVERGENCE AND SPECIAL SUPPORT PROGRAM -SUSTAINABLE INFRASTRUCTURE PROJECTS ALLEVIATING GAPS (SIPAG) - ACCESS ROADS AND/OR BRIDGES FROM THE NATIONAL HIGHWAY ROAD/S LEADING TO MAJOR/STRATEGIC PUBLIC BUILDINGS/FACILITIES - CONSTRUCTION OF ROAD, BRGY. POBLA

Bohol 3rd DEO, Region VII

2022₱29.4M
Reported complete (DPWH)
No sat.

BASIC EDUCATIONAL FACILITIES FUND (BEFF)- BATCH 1: CONSTRUCTION OF 2STY6CL SCHOOL BUILDING, CANMAYA DIOT HIGH SCHOOL, SAGBAYAN, BOHOL

Bohol 2nd DEO, Region VII

2023₱20.0M
Reported complete (DPWH)
No sat.

CONVERGENCE AND SPECIAL SUPPORT PROGRAM -SUSTAINABLE INFRASTRUCTURE PROJECTS ALLEVIATING GAPS (SIPAG) - ACCESS ROADS AND / OR BRIDGES FROM THE NATIONAL ROADS LEADING TO MAJOR / STRATEGIC PUBLIC BUILDING / FACILITIES - CONSTRUCTION OF ROAD, SITIO KAWASAN

Bohol 3rd DEO, Region VII

2022₱19.6M
Reported complete (DPWH)
No sat.

COMPLETION OF ALBURQUERQUE PUBLIC MARKET

Bohol 1st DEO, Region VII

2019₱14.8M
Reported complete (DPWH)
No sat.

CONVERGENCE AND SPECIAL SUPPORT PROGRAM - CONSTRUCTION/ IMPROVEMENT OF ACCESS ROADS LEADING TO TRADES, INDUSTRIES AND ECONOMIC ZONES (ROADS LEVERAGING LINKAGES FOR INDUSTRY AND TRADE INFRASTRUCTURE PROGRAM - ROLL-IT) - JCT. (LIR) BUENOS AIRES-NUEVA VIDA (

Bohol 3rd DEO, Region VII

2024₱14.7M
Reported complete (DPWH)
View all 93 projects →

4. Implementation

Contract Amount

₱940,168.00

Progress

Reported complete (DPWH)

Start Date

July 30, 2019

Target End

August 30, 2019

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.

Connected records

Where this project sits

Place (PSGC)
Region VII (Central Visayas)BoholSevillaLicolico
Storms whose wind field reached it
None on record (IBTrACS tracks).
Hazard exposure
No medium/high hazard on the mapped layers.Details in Hazard context above.Full hazard check →
El Niño outlook (province)
No PAGASA drought or dry flag for this province.El Niño readiness →

Exposure to a storm, hazard or drought outlook is context, not a finding about the project.