Roads15L00039

ROAD UPGRADING (GRAVEL TO CONCRETE) OF KAPALONG-TALAINGOD-VALENCIA(BUKIDNON) RD,DAVAO DEL NORTE, STA

ROAD UPGRADING (GRAVEL TO CONCRETE) OF KAPALONG-TALAINGOD-VALENCIA(BUKIDNON) RD,DAVAO DEL NORTE, STA is a DPWH-tracked public work in Region XI, Region XI. Reported contract value: ₱107,025,083.00. Status: Reported complete (DPWH). Contractor on record: ULTICON BUILDERS INC. Figures trace to dpwh.

Region XI, Region XI
Region: Region XI

Follow the peso

2 of 5 steps linked to this project. Links are automated matches unless marked confirmed.

  1. 1. GAA budget line

    No GAA line found for this project's office and year. The GAA lists budgets by program and office, not always by project.

  2. 2. SARO / NCA release

    No SARO/NCA found for this office and year. DBM publishes releases by agency and office, rarely by project.

  3. 3. PhilGEPS award

    ₱107,025,778 · ULTICON BUILDERS INC

    Confirmed (exact contract ID) · score 1.00

    PhilGEPS source ↗
  4. 4. DPWH progress + satellite

    100% reported · imagery 2013-09-15 → 2020-04-12

    Same record (DPWH contract ID)

    DPWH Transparency Portal source ↗
  5. 5. COA audit finding

    No COA finding names this project. COA audits DPWH by office each year; project-level findings are only linked when the report names the contract.

Been to this site?

Share a photo of what is there today. Faces and vehicle plates are blurred automatically, all photo metadata except the date and location is removed, and nothing is published until a moderator approves it.

Watch this project

Get a weekly email when this project changes: progress, new linked records or newly published anomaly flags.

Share card: ROAD UPGRADING (GRAVEL TO CONCRETE) OF KAPALONG-TALAINGOD-VALENCIA(BUKIDNON) RD,DAVAO DEL NORTE, STA

Share this page

The card shows the public record facts and a QR code back to this page.

FacebookDownload image

Money Trail

1. Appropriation

No matching GAA line found for this project in the FY2016 GAA. DBM GAA FY2016

2. Allotment

No matching SARO/NCA release found for this project. Source: DBM SARO/NCA listings.

3. Procurement & Award

Confirmed (exact contract ID) · 100%

15L00039 ROA, NOA, Contract & Notice to Proceed

₱107,025,777.88 · ULTICON BUILDERS INC

Award / contract ref: 15L00039

Contractor

C

546 projects · ₱133.2B total · 0 flags

4. Implementation

Contract Amount

₱107,025,083.00

Progress

Reported complete (DPWH)

Start Date

February 17, 2016

Target End

May 6, 2018

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.

Connected records

Where this project sits

Place (PSGC)
Region XI (Davao Region)Davao del NorteTalaingodPalma Gil
Storms whose wind field reached it
None on record (IBTrACS tracks).
Hazard exposure
LandslideDetails in Hazard context above.Full hazard check →
El Niño outlook (province)
No PAGASA drought or dry flag for this province.El Niño readiness →

Exposure to a storm, hazard or drought outlook is context, not a finding about the project.