GAA 2025 DA FMR25HH0152

CONCRETING OF BRGY. SAN JOSE FMR, BRGY. JOSE, CEBU CITY

CONCRETING OF BRGY. SAN JOSE FMR, BRGY. JOSE, CEBU CITY is a DPWH-tracked public work in Cebu City DEO, Region VII. Reported contract value: ₱14,910,000.00. Status: Reported complete (100% progress, DPWH status On-Going). Contractor on record: VNCO CONST. Figures trace to dpwh.

Cebu City DEO, Region VII
Region: Region VII

Follow the peso

2 of 5 steps linked to this project, 1 at office level only. Links are automated matches unless marked confirmed.

  1. 1. GAA budget line

    FY2025 · ₱5,000

    Probable match · score 0.85

    DBM GAA source ↗
  2. 2. SARO / NCA release

    NCA NCA-BMB-E-25-0008820 · ₱2,391,464,864 · release to the district office, not itemized per project

    Possible match · score 0.63

    DBM release source ↗
  3. 3. PhilGEPS award

    Not found in PhilGEPS by contract ID 25HH0152 or title. The open PhilGEPS mirror does not include every DPWH notice.

  4. 4. DPWH progress + satellite

    100% reported · imagery 2025-01-18 → 2026-02-04

    Same record (DPWH contract ID)

    DPWH Transparency Portal source ↗
  5. 5. COA audit finding

    No COA finding names this project. COA audits DPWH by office each year; project-level findings are only linked when the report names the contract.

Been to this site?

Share a photo of what is there today. Faces and vehicle plates are blurred automatically, all photo metadata except the date and location is removed, and nothing is published until a moderator approves it.

Watch this project

Get a weekly email when this project changes: progress, new linked records or newly published anomaly flags.

Share card: CONCRETING OF BRGY. SAN JOSE FMR, BRGY. JOSE, CEBU CITY

Share this page

The card shows the public record facts and a QR code back to this page.

FacebookDownload image

Money Trail

1. Appropriation

Probable match · score 85%

UACS
18001
Amount
₱5,000,000.00 (GAA By-Object, amounts in ₱'000 × 1,000)
Program / description
Construction of Flood Mitigation Structure, Brgy. Carreta , Cebu City
GAA fiscal year
FY2025
DBM GAA source document

2. Allotment

Office-level release, not tied to this specific contract

NCA NCA-BMB-E-25-0008820

₱2,391,464,863.61 · FY2025

Released to Central Office (office-level, not project-specific). This SARO/NCA funds the office's programme; DBM listings do not tie it to this contract.

DBM NCA listing (source)

3. Procurement & Award

No PhilGEPS award linked in the link table for this contract yet.

Contractor

D

65 projects · ₱380.6M total · 0 flags

Other projects by this contractor

No sat.

OO1: ENSURE SAFE AND RELIABLE NATIONAL ROAD SYSTEM- ASSET PRESERVATION PROGRAM- PREVENTIVE MAINTENANCE -SECONDARY ROADS- CEBU - BALAMBAN TRANSCENTRAL HIGHWAY - K0013+530 - K0014+190, CEBU CITY

Cebu City DEO, Region VII

2022₱15.6M
Reported complete (DPWH)
No sat.

CAPITAL OUTLAY - FARM-TO-MARKET ROAD (FMR) PROJECTS, REPAIR/REHABILITATION AND CONSTRUCTION OF FARM-TO-MARKET ROADS, CONCRETING OF BRGY. TACLOBAN TO NRGY. OLO FMR, BRGY. TACLOBAN, SIQUIJOR, SIQUIJOR

Siquijor DEO, Negros Island Region

2025₱14.6M
Past target date (DPWH On-Going)
No sat.

CONCRETING OF BRGY. BONBON FMR, BRGY. BONBON, CEBU CITY, CEBU

Cebu City DEO, Region VII

2021₱12.2M
Reported complete (DPWH)
No sat.

OO1: ENSURE SAFE AND RELIABLE NATIONAL ROAD SYSTEM, ASSET PRESERVATION PROGRAM, REHABILITATION/ RECONSTRUCTION/ UPGRADING OF DAMAGED PAVED ROADS - SECONDARY ROADS, SIQUIJOR CIRCUMFERENTIAL RD - K0071+648 - K0072+000

Siquijor DEO, Negros Island Region

2025₱12.0M
Reported complete (100% progress, DPWH status On-Going)
No sat.

OO1: ENSURE SAFE AND RELIABLE NATIONAL ROAD SYSTEM, ASSET PRESERVATION PROGRAM, REHABILITATION/ RECONSTRUCTION/ UPGRADING OF DAMAGED PAVED ROADS - SECONDARY ROADS. SIQUIJOR CIRCUMFERENTIAL RD - K0069+660 - K0070+000

Siquijor DEO, Negros Island Region

2025₱11.9M
Past target date (DPWH On-Going)
No sat.

OO1: ENSURE SAFE AND RELIABLE NATIONAL ROAD SYSTEM, ASSET PRESERVATION PROGRAM, REHABILITATION/ RECONSTRUCTION/ UPGRADING OF DAMAGED PAVED ROADS - SECONDARY ROADS, SIQUIJOR CIRCUMFERENTIAL RD - K0070+663 - K0071+000

Siquijor DEO, Negros Island Region

2025₱11.7M
Past target date (DPWH On-Going)
View all 65 projects →

4. Implementation

Contract Amount

₱14,910,000.00

Progress

Reported complete (100% progress, DPWH status On-Going)

Start Date

April 10, 2025

Target End

August 26, 2025

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.

Connected records

Where this project sits

Place (PSGC)
Region VII (Central Visayas)City of CebuSan Jose
Storms whose wind field reached it
None on record (IBTrACS tracks).
Hazard exposure
Active faultLandslideDetails in Hazard context above.Full hazard check →
El Niño outlook (province)
No province on record.El Niño readiness →

Exposure to a storm, hazard or drought outlook is context, not a finding about the project.