Flood Control and Drainage17FH0003No coordinates published by DPWH

CONSTRUCTION/MAINTENANCE OF FLOOD MITIGATION STRUCTURES AND DRAINAGE SYSTEMS, CONSTRUCTION OF SAN JOAQUIN-SAN PEDRO RIVER CONTROL, PANGANIBAN, CATANDUANES

CONSTRUCTION/MAINTENANCE OF FLOOD MITIGATION STRUCTURES AND DRAINAGE SYSTEMS, CONSTRUCTION OF SAN JOAQUIN-SAN PEDRO RIVER CONTROL, PANGANIBAN, CATANDUANES is a DPWH-tracked public work in Catanduanes DEO, Region V. Reported contract value: ₱39,199,695.83. Status: Reported complete (DPWH). Contractor on record: NFH CONST. Figures trace to dpwh.

Catanduanes DEO, Region V

DPWH did not publish coordinates for this project. Location estimated from the project title (town level only); satellite images may not show the exact site.

Region: Region V

No before/after satellite images: DPWH did not publish coordinates, and the location estimated from the project title is only town level, which is not confident enough to image.

Follow the peso

3 of 5 steps linked to this project, 1 at office level only. Links are automated matches unless marked confirmed.

  1. 1. GAA budget line

    FY2017 · ₱5,000

    Probable match · score 0.86

    DBM GAA source ↗
  2. 2. SARO / NCA release

    SARO SARO-BMB-E-17-0011469 · ₱5,880,000 · release to the district office, not itemized per project

    Possible match · score 0.70

    DBM release source ↗
  3. 3. PhilGEPS award

    ₱37,180,730 · NFH CONSTRUCTION & SUPPLY

    Confirmed (exact contract ID) · score 1.00

    PhilGEPS source ↗
  4. 4. DPWH progress + satellite

    100% reported · no satellite pair yet

    Same record (DPWH contract ID)

    DPWH Transparency Portal source ↗
  5. 5. COA audit finding

    No COA finding names this project. COA audits DPWH by office each year; project-level findings are only linked when the report names the contract.

Been to this site?

Share a photo of what is there today. Faces and vehicle plates are blurred automatically, all photo metadata except the date and location is removed, and nothing is published until a moderator approves it.

Watch this project

Get a weekly email when this project changes: progress, new linked records or newly published anomaly flags.

Share card: CONSTRUCTION/MAINTENANCE OF FLOOD MITIGATION STRUCTURES AND DRAINAGE SYSTEMS, CONSTRUCTION OF SAN JOAQUIN-SAN PEDRO RIVER CONTROL, PANGANIBAN, CATANDUANES

Share this page

The card shows the public record facts and a QR code back to this page.

FacebookDownload image

Money Trail

1. Appropriation

Probable match · score 86%

UACS
18001
Amount
₱5,000,000.00 (GAA By-Object, amounts in ₱'000 × 1,000)
Program / description
Construction of Bagong Sirang Flood Control, Baras, Catanduanes
GAA fiscal year
FY2017
DBM GAA source document

2. Allotment

Office-level release, not tied to this specific contract

SARO SARO-BMB-E-17-0011469

₱5,880,000.00 · FY2017

Released to PENRO Zamboanga Modifi del Norte Expens develo Zamboa (office-level, not project-specific). This SARO/NCA funds the office's programme; DBM listings do not tie it to this contract.

DBM SARO listing (source)

3. Procurement & Award

Confirmed (exact contract ID) · 100%

CONSTRUCTION/MAINTENANCE OF FLOOD MITIGATION STRUC

₱37,180,729.72 · NFH CONSTRUCTION & SUPPLY

Award / contract ref: 17FH0003

Contractor

B

123 projects · ₱5.3B total · 0 flags

Other projects by this contractor

No sat.

OO1: ENSURE SAFE AND RELIABLE NATIONAL ROAD SYSTEM-NETWORK DEVELOPMENT PROGRAM-CONSTRUCTION OF BYPASS AND DIVERSION ROADS-MABOLO-ALMEDA BYPASS ROAD, NAGA CITY, CAMARINES SUR 3RD LEGISLATIVE DISTRICT

Region V, Region V

2021₱226.8M
Reported complete (DPWH)
No sat.

CONST./IMPV'T. OF ACCESS ROADS LEADING TO AIRPORTS, SEAPORTS AND DECLARED TOURISM DESTINATIONS - JCT. MORNING, CATAINGAN-ESPERANZA PORT ROAD, PIO V. CORPUZ AND ESPERANZA, MASBATE 3RD LD

Region V, Region V

2016₱202.4M
Reported complete (DPWH)
No sat.

OO1: ENSURE SAFE AND RELIABLE NATIONAL ROAD SYSTEM-NETWORK DEVELOPMENT PROGRAM-CONSTRUCTION OF BY-PASS AND DIVERSION ROADS-CAMARINES SUR EXPRESSWAY PACKAGE 7, CAMARINES SUR, PILI, CAMARINES SUR (3RD LEGISLATIVE DISTRICT)

Region V, Region V

2023₱193.0M
Past target date (DPWH On-Going)
No sat.

ORGANIZATIONAL OUTCOME 1 : ENSURE SAFE AND RELIABLE NATIONAL ROAD SYSTEM-ASSET PRESERVATION PROGRAM-PREVENTIVE MAINTENANCE-SECONDARY ROADS -NASUGBU-LIAN-CALATAGAN RD (S05012LZ) - K0113 + 600 - K0114 + 000, K0115 + 000 - K0116 + 400

Batangas 1st DEO, Region IV-A

2024₱144.8M
Reported complete (DPWH)
No sat.

CONST./IMPV'T. OF ACCESS ROADS LEADING TO DECLARED TOURISM DESTINATIONS, ROAD UPGRADING (GRAVEL TO CONCRETE) OF SAN JUAN-ALAS-TAGPU-DAYAO ROAD LEADING TO MANDAON ECOTOURISM SITES, MANDAON, MASBATE PROVINCE

Region V, Region V

2016₱144.7M
Reported complete (DPWH)
No sat.

ROAD UPGRADING (UNPAVED TO PAVED) BASED ON GRAVEL ROAD STRATEGIES, TRAFFIC BENCHMARK FOR UPGRADING TO PAVED ROAD STANDARDS (HDM-4 PROJECT ANALYSIS) STA. ELENA - CAPALONGA BY PASS COASTAL ROAD, KO283+040 - KO292+200 WITH EXCEPTIONS, CAMARINES NORTE

Region V, Region V

2016₱142.9M
Reported complete (DPWH)
View all 123 projects →

4. Implementation

Contract Amount

₱39,199,695.83

Progress

Reported complete (DPWH)

Start Date

March 20, 2017

Target End

December 14, 2017

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.

Connected records

Where this project sits

Place (PSGC)
Region V (Bicol Region)CatanduanesPanganiban
Storms whose wind field reached it
None on record (IBTrACS tracks).
Hazard exposure
LandslideDetails in Hazard context above.Full hazard check →
El Niño outlook (province)
Drought / dry spell likelyPAGASA · 2026-11-03El Niño readiness →

Exposure to a storm, hazard or drought outlook is context, not a finding about the project.