Bridges25IH0008

CONSTRUCTION OF BRIDGE, BARANGAY AGUINALDO, CATARMAN, NORTHERN SAMAR

CONSTRUCTION OF BRIDGE, BARANGAY AGUINALDO, CATARMAN, NORTHERN SAMAR is a DPWH-tracked public work in Northern Samar 1st DEO, Region VIII. Reported contract value: ₱14,694,811.84. Status: Past target date (DPWH On-Going). Contractor on record: SMU CONST AND SUPPLY. Figures trace to dpwh.

Northern Samar 1st DEO, Region VIII
Region: Region VIII

Satellite images processing — before/after tiles will appear here after the next batch run.

Money Trail

1. Appropriation

Probable match · score 86%

UACS
18001
Amount
₱40,000,000.00 (GAA By-Object, amounts in ₱'000 × 1,000)
Program / description
Construction (Completion) of Flood Control Structures, Barangay San Lorenzo, San Jose, Northern Samar
GAA fiscal year
FY2025
DBM GAA source document

2. Allotment

Office-level release, not tied to this specific contract

NCA NCA-ROII-25-0011367

₱778,264.00 · FY2025

Released to Northern Samar 1st DEO (office-level, not project-specific). This SARO/NCA funds the office's programme; DBM listings do not tie it to this contract.

DBM NCA listing (source)

3. Procurement & Award

No PhilGEPS award linked in the link table for this contract yet.

4. Implementation

Contract Amount

₱14,694,811.84

Progress

Past target date (DPWH On-Going)

Start Date

February 25, 2025

Target End

September 6, 2025

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.