Roads17K00216

CONST. OF BY-PASSES/DIVERSION ROADS,SH BY-PASS RD(CLIMBING LANES)INCL. ROW,CARMEN-PUERTO SECT.,CDOC

CONST. OF BY-PASSES/DIVERSION ROADS,SH BY-PASS RD(CLIMBING LANES)INCL. ROW,CARMEN-PUERTO SECT.,CDOC is a DPWH-tracked public work in Region X, Region X. Reported contract value: ₱157,836,489.39. Status: Reported complete (DPWH). Contractor on record: DL ENT. Figures trace to dpwh.

Region X, Region X
Region: Region X

Money Trail

1. Appropriation

No matching GAA line found for this project in the FY2017 GAA. DBM GAA FY2017

2. Allotment

No matching SARO/NCA release found for this project. Source: DBM SARO/NCA listings.

3. Procurement & Award

4. Implementation

Contract Amount

₱157,836,489.39

Progress

Reported complete (DPWH)

Start Date

March 2, 2017

Target End

November 22, 2018

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.