Roads22FL0056

CONSTRUCTION OF MILIGA-BIGA ROAD, BULUSAN, SORSOGON

CONSTRUCTION OF MILIGA-BIGA ROAD, BULUSAN, SORSOGON is a DPWH-tracked public work in Sorsogon 2nd DEO, Region V. Reported contract value: ₱9,502,125.32. Status: Reported complete (DPWH). Contractor on record: YENZ CONST. Figures trace to dpwh.

Sorsogon 2nd DEO, Region V
Region: Region V

Follow the peso

2 of 5 steps linked to this project, 1 at office level only. Links are automated matches unless marked confirmed.

  1. 1. GAA budget line

    FY2022 · ₱30,000

    Probable match · score 0.85

    DBM GAA source ↗
  2. 2. SARO / NCA release

    SARO SARO-ROXI-22-0008618 · ₱1,792,601 · release to the district office, not itemized per project

    Possible match · score 0.61

    DBM release source ↗
  3. 3. PhilGEPS award

    Not found in PhilGEPS by contract ID 22FL0056 or title. The open PhilGEPS mirror does not include every DPWH notice.

  4. 4. DPWH progress + satellite

    100% reported · imagery 2022-06-20 → 2022-06-20

    Same record (DPWH contract ID)

    DPWH Transparency Portal source ↗
  5. 5. COA audit finding

    No COA finding names this project. COA audits DPWH by office each year; project-level findings are only linked when the report names the contract.

Been to this site?

Share a photo of what is there today. Faces and vehicle plates are blurred automatically, all photo metadata except the date and location is removed, and nothing is published until a moderator approves it.

Watch this project

Get a weekly email when this project changes: progress, new linked records or newly published anomaly flags.

Share card: CONSTRUCTION OF MILIGA-BIGA ROAD, BULUSAN, SORSOGON

Share this page

The card shows the public record facts and a QR code back to this page.

FacebookDownload image

Money Trail

1. Appropriation

Probable match · score 85%

UACS
18001
Amount
₱30,000,000.00 (GAA By-Object, amounts in ₱'000 × 1,000)
Program / description
Construction of Flood Control Structure in Monbon, Irosin, Sorsogon
GAA fiscal year
FY2022
DBM GAA source document

2. Allotment

Office-level release, not tied to this specific contract

SARO SARO-ROXI-22-0008618

₱1,792,601.00 · FY2022

Released to Division of Panabo City (office-level, not project-specific). This SARO/NCA funds the office's programme; DBM listings do not tie it to this contract.

DBM SARO listing (source)

3. Procurement & Award

No PhilGEPS award linked in the link table for this contract yet.

4. Implementation

Contract Amount

₱9,502,125.32

Progress

Reported complete (DPWH)

Start Date

September 1, 2022

Target End

November 17, 2022

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.

Connected records

Where this project sits

Place (PSGC)
Region V (Bicol Region)SorsogonBulusanSan Bernardo
Storms whose wind field reached it
None on record (IBTrACS tracks).
Hazard exposure
No medium/high hazard on the mapped layers.Details in Hazard context above.Full hazard check →
El Niño outlook (province)
Drought / dry spell likelyPAGASA · 2026-10-07El Niño readiness →

Exposure to a storm, hazard or drought outlook is context, not a finding about the project.