Bridges24B00049

OO1: ENSURE SAFE AND RELIABLE NATIONAL ROAD SYSTEM: BRIDGE PROGRAM - CONSTRUCTION OF NEW BRIDGES - BUCAO BR. ALONG JCT ABBAG - NAGTIPUNAN - NUEVA VIZCAYA RD VIA DUPAX

OO1: ENSURE SAFE AND RELIABLE NATIONAL ROAD SYSTEM: BRIDGE PROGRAM - CONSTRUCTION OF NEW BRIDGES - BUCAO BR. ALONG JCT ABBAG - NAGTIPUNAN - NUEVA VIZCAYA RD VIA DUPAX is a DPWH-tracked public work in Region II, Region II. Reported contract value: ₱48,024,605.19. Status: Past target date (DPWH On-Going). Contractor on record: C-BROS CONST. Figures trace to dpwh.

Region II, Region II
Region: Region II

Satellite images processing — before/after tiles will appear here after the next batch run.

Money Trail

1. Appropriation

No matching GAA line found for this project in the FY2024 GAA. DBM GAA FY2024

2. Allotment

No matching SARO/NCA release found for this project. Source: DBM SARO/NCA listings.

3. Procurement & Award

No PhilGEPS award linked in the link table for this contract yet.

Contractor

A

106 projects · ₱1.2B total · 0 flags

Other projects by this contractor

No sat.

OO1: ENSURE SAFE AND RELIABLE NATIONAL ROAD SYSTEM: NETWORK DEVELOPMENT - CONSTRUCTION OF MISSING LINKS/ NEW ROADS - ARITAO-QUIRINO ROAD (UMASOK BR. AND APPROACHES), PACKAGE 2, QUIRINO

Region II, Region II

2024₱144.6M
Reported complete (100% progress, DPWH status On-Going)
No sat.

ORGANIZATIONAL OUTCOME 1: ENSURE SAFE AND RELIABLE NATIONAL ROAD SYSTEM - NETWORK DEVELOPMENT PROGRAM - CONSTRUCTION OF MISSING LINKS/NEW ROADS - AGUINALDO - TOBOY - NATONIN ROADAGUINALDO IFUGAO

Cordillera Administrative Region, Cordillera Administrative Region

2022₱118.2M
Reported complete (DPWH)
No sat.

ORGANIZATIONAL OUTCOME 1: ENSURE SAFE AND RELIABLE NATIONAL ROAD SYSTEM - ASSET PRESERVATION PROGRAM - PREVENTIVE MAINTENANCE - SECONDARY ROADS BANAUE - MAYOYAO - A. LISTA - ISABELA BDRY ROAD, KO341+(-880) - KO341+(-252), KO341+(-069) - KO348+187

Cordillera Administrative Region, Cordillera Administrative Region

2020₱116.5M
Reported complete (DPWH)
No sat.

ORGANIZATIONAL OUTCOME 1: ENSURE SAFE AND RELIABLE NATIONAL ROAD SYSTEM - ASSET PRESERVATION PROGRAM - REHABILITATION/ RECONSTRUCTION OF ROADS WITH SLIPS, SLOPE COLLAPSE, AND LANDSLIDE - TERTIARY ROADS BANAUE - HUNGDUAN - BENGUET BDRY ROAD, KO407+480 - KO

Cordillera Administrative Region, Cordillera Administrative Region

2021₱114.1M
Reported complete (DPWH)
No sat.

BRIDGE PROGRAM - REPLACEMENT OF PERMANENT WEAK BRIDGES - DUMABATO BR. (B04453LZ) ALONG DUMABATO-BALLIGUI RD, MADDELA, QUIRINO

Quirino DEO, Region II

2023₱96.5M
Reported complete (DPWH)
No sat.

REHABILITATION/RECONSTRUCTION OF NATIONAL ROADS WITH SLIPS, SLOPE COLLAPSE AND LANDSLIDES ALONG NUEVA VIZCAYA-IFUGAO-MT. PROVINCE ROAD, KO296+000,KO296+1038-KO297+210,KO301+807-KO301+917,KO307+698,KO320+545-KO320+605,KO322+632,KO332+377-KO332+407,KO333+18

Ifugao 1st DEO, Cordillera Administrative Region

2020₱72.0M
Reported complete (DPWH)
View all 106 projects →

4. Implementation

Contract Amount

₱48,024,605.19

Progress

Past target date (DPWH On-Going)

Start Date

July 26, 2024

Target End

May 6, 2025

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.