Roads22DD0180

CONVERGENCE AND SPECIAL SUPPORT PROGRAM, BASIC INFRASTRUCTURE PROGRAM (BIP), ACCESS ROADS AND/OR BRIDGES FROM THE NATIONAL ROAD/S LEADING TO MAJOR/ STRATEGIC PUBLIC BUILDINGS/ FACILITIES, REHABILITATION OF TAYSAN - ROSARIO ROAD, TAYSAN, BATANGAS

CONVERGENCE AND SPECIAL SUPPORT PROGRAM, BASIC INFRASTRUCTURE PROGRAM (BIP), ACCESS ROADS AND/OR BRIDGES FROM THE NATIONAL ROAD/S LEADING TO MAJOR/ STRATEGIC PUBLIC BUILDINGS/ FACILITIES, REHABILITATION OF TAYSAN - ROSARIO ROAD, TAYSAN, BATANGAS is a DPWH-tracked public work in Batangas 4th DEO, Region IV-A. Reported contract value: ₱53,053,025.00. Status: Reported complete (DPWH). Contractor on record: N D M SANCHEZ BUILDERS & DEVELOPMENT CORP. Figures trace to dpwh.

Batangas 4th DEO, Region IV-A
Region: Region IV-A

Money Trail

1. Appropriation

Possible match · score 81%

UACS
18001
Amount
₱10,000,000.00 (GAA By-Object, amounts in ₱'000 × 1,000)
Program / description
Construction/Rehabilitation of Flood Mitigation Structures protecting Public Infrastructures/ Facilities at Barangay Quezon, Lipa City, Batangas
GAA fiscal year
FY2022
DBM GAA source document

2. Allotment

Office-level release, not tied to this specific contract

NCA NCA-NCR-22-0002043

₱9,823,970.91 · FY2022

Source

3. Procurement & Award

No PhilGEPS award linked in the link table for this contract yet.

Contractor

26 projects · ₱2.1B total · 2 flags

Other projects by this contractor

No sat.

ENSURE SAFE & RELIABLE NAT'L. ROAD SYSTEM, NETWORK DEVELOPMENT PROGRAM, CONST. OF BY-PASS & DIVERSION ROADS, ALAMINOS-SAN PABLO CITY BY-PASS ROAD, INCL. ROW AND BRIDGE, LAGUNA

Region IV-A, Region IV-A

2018₱182.5M
Reported complete (DPWH)
No sat.

FY 2017 DPWH INFRASTRUCTURE PROGRAMMFO-1 NATIONAL ROAD NETWORK SERVICESNETWORK DEVELOPMENT CONSTRUCTION OF BY-PASSES/DIVERSION RDS, INCL ROWALAMINOS-SAN PABLO CITY BY-PASS ROAD, INCL BRIDGE AND ROW, LAGUNA 3RD LD, LAGUNA PROVINCE

Region IV-A, Region IV-A

2017₱140.3M
Reported complete (DPWH)
No sat.

FY 2020 DPWH INFRASTRUCTURE PROGRAM ORGANIZATIONAL OUTCOME 1: ENSURE SAFE AND RELIABLE NATIONAL ROAD SYSTEM NETWORK DEVELOPMENT PROGRAM CONSTRUCTION OF BY-PASS AND DIVERSION ROADS ALAMINOS-SAN PABLO CITY BY-PASS, PACKAGE C, LAGUNA

Region IV-A, Region IV-A

2020₱116.9M
Reported complete (DPWH)
No sat.

MFO-1 CONST. OF BY-PASSES/DIV. ROAD, INCL. ROW, ALAMINOS-SAN PABLO CITY BYPASS LAGUNA 3RD LD, LAGUNA

Region IV-A, Region IV-A

2016₱112.0M
Reported complete (DPWH)
No sat.

FY 2020 DPWH INFRASTRUCTURE PROGRAMORGANIZATIONAL OUTCOME 1:ENSURE SAFE AND RELIABLE NATIONAL ROAD SYSTEMNETWORK DEVELOPMENT PROGRAM CONSTRUCTION OF BY-PASS AND DIVERSION ROADSALAMINOS SAN PABLO CITY BYPASS, PACKAGE D, LAGUNA

Region IV-A, Region IV-A

2020₱107.6M
Reported complete (DPWH)
No sat.

FY 2021 DPWH INFRASTRUCTURE PROGRAM ORGANIZATIONAL OUTCOME 1: ENSURE SAFE AND RELIABLE NATIONAL ROAD SYSTEM NETWORK DEVELOPMENT PROGRAM CONSTRUCTION OF BY-PASS AND DIVERSION ROADS ALAMINOS - SAN PABLO BYPASS ROAD, PACKAGE E, LAGUNA

Region IV-A, Region IV-A

2021₱105.9M
Reported complete (DPWH)
View all 26 projects →

4. Implementation

Contract Amount

₱53,053,025.00

Progress

Reported complete (DPWH)

Start Date

March 29, 2022

Target End

October 29, 2022

5. Audit