Buildings and Facilities23BD0072

BASIC INFRASTRUCTURE PROGRAM - MULTI- PURPOSE BUILDINGS/ FACILITIES TO SUPPORT SOCIAL SERVICES - CONSTRUCTION (COMPLETION) OF MULTI-PURPOSE BUILDING (CONVERTIBLE TO EVACUATION CENTER), BARANGAY FURAGUI, SOLANA, CAGAYAN

BASIC INFRASTRUCTURE PROGRAM - MULTI- PURPOSE BUILDINGS/ FACILITIES TO SUPPORT SOCIAL SERVICES - CONSTRUCTION (COMPLETION) OF MULTI-PURPOSE BUILDING (CONVERTIBLE TO EVACUATION CENTER), BARANGAY FURAGUI, SOLANA, CAGAYAN is a DPWH-tracked public work in Cagayan 3rd DEO, Region II. Reported contract value: ₱2,475,000.00. Status: Reported complete (DPWH). Contractor on record: COLORSHIELD CONST AND DEVELOPMENT CORP. Figures trace to dpwh.

Cagayan 3rd DEO, Region II
Region: Region II

Money Trail

1. Appropriation

Possible match · score 83%

UACS
18001
Amount
₱30,000,000.00 (GAA By-Object, amounts in ₱'000 × 1,000)
Program / description
Construction of Flood Control Structures along Pinacanauan River, Barangay Quibal, Pe±ablanca, Cagayan
GAA fiscal year
FY2023
DBM GAA source document

2. Allotment

Office-level release, not tied to this specific contract

SARO SARO-BMB-A-23-0024446

₱679,288.00 · FY2023

Source

3. Procurement & Award

No PhilGEPS award linked in the link table for this contract yet.

Contractor

14 projects · ₱85.8M total · 0 flags

Other projects by this contractor

No sat.

CONSTRUCTION OF MULTI-PURPOSE COVERED COURT, BRGY. ALIBAGU, ILAGAN CITY, ISABELA

Isabela 1st DEO, Region II

2024₱28.9M
Past target date (DPWH On-Going)
No sat.

LOCAL PROGRAM - NATIONAL BUILDING PROGRAM - BUILDINGS AND OTHER STRUCTURES - MULTIPURPOSE / FACILITIES - CONSTRUCTION OF BUREAU OF FIRE PROTECTION (BFP) PROVINCIAL OFFICE, PEÑABLANCA, CAGAYAN

Cagayan 3rd DEO, Region II

2024₱11.6M
Reported complete (100% progress, DPWH status On-Going)
No sat.

BASIC INFRASTRUCTURE PROGRAM (BIP) - MULTI-PURPOSE BUILDINGS/FACILITIES TO SUPPORT SOCIAL SERVICES - CONSTRUCTION OF MULTI-PURPOSE BUILDING BARANGAY PENGUE-RUYU, TUGUEGARAO CITY, CAGAYAN

Cagayan 3rd DEO, Region II

2025₱9.6M
Past target date (DPWH On-Going)
No sat.

LOCAL PROGRAM - NATIONAL BUILDING PROGRAM - BUILDINGS AND OTHER STRUCTURES - MULTIPURPOSE/FACILITIES - CONSTRUCTION OF BUREAU OF FIRE PROTECTION (BFP) PROVINCIAL OFFICE, PEÑABLANCA, CAGAYAN - PHASE II

Cagayan 3rd DEO, Region II

2025₱6.8M
Past target date (DPWH On-Going)
No sat.

LOCAL PROGRAM - NATIONAL BUILDING PROGRAM - BUILDINGS AND OTHER STRUCTURES - MULTIPURPOSE / FACILITIES - CONSTRUCTION OF CIVIL SERVICE COMMISSION RO2 OFFICE BUILDING, REGIONAL GOVERNMENT CENTER, CARIG SUR, TUGUEGARAO CITY, CAGAYAN PHASE II

Cagayan 3rd DEO, Region II

2023₱4.9M
Reported complete (DPWH)
No sat.

BASIC INFRASTRUCTURE PROGRAM (BIP) - MULTI-PURPOSE BUILDINGS / FACILITIES TO SUPPORT SOCIAL SERVICES - CONSTRUCTION OF MULTI-PURPOSE BUILDING, BALIWAG ELEMENTARY SCHOOL, PEÑABLANCA, CAGAYAN

Cagayan 3rd DEO, Region II

2025₱4.8M
Past target date (DPWH On-Going)
View all 14 projects →

4. Implementation

Contract Amount

₱2,475,000.00

Progress

Reported complete (DPWH)

Start Date

April 27, 2023

Target End

August 24, 2023

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.