Buildings and Facilities24IE0085

CONSTRUCTION (COMPLETION) OF MULTI-PURPOSE BUILDING, BARANGAY TINUCDUCAN, LEYTE, LEYTE

CONSTRUCTION (COMPLETION) OF MULTI-PURPOSE BUILDING, BARANGAY TINUCDUCAN, LEYTE, LEYTE is a DPWH-tracked public work in Leyte 3rd DEO, Region VIII. Reported contract value: ₱1,946,994.22. Status: Reported complete (DPWH). Contractor on record: ALPLAN BUILDERS. Figures trace to dpwh.

Leyte 3rd DEO, Region VIII
Region: Region VIII

Satellite images processing — before/after tiles will appear here after the next batch run.

Money Trail

1. Appropriation

Possible match · score 85%

UACS
18001
Amount
₱50,000,000.00 (GAA By-Object, amounts in ₱'000 × 1,000)
Program / description
Construction of Flood Control Structure, Barangay Jalas, Villaba, Leyte
GAA fiscal year
FY2024
DBM GAA source document

2. Allotment

Office-level release, not tied to this specific contract

NCA NCA-ROXII-24-0013236

₱1,711,243.00 · FY2024

Released to Matalam High School (Poblacion) (office-level, not project-specific). This SARO/NCA funds the office's programme; DBM listings do not tie it to this contract.

DBM NCA listing (source)

3. Procurement & Award

4. Implementation

Contract Amount

₱1,946,994.22

Progress

Reported complete (DPWH)

Start Date

October 10, 2024

Target End

January 2, 2025

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.