Buildings and Facilities25CD0132

CONSTRUCTION OF MULTI-PURPOSE BUILDING, BARANGAY SAN MARTIN I, SAN JOSE DEL MONTE CITY, BULACAN

CONSTRUCTION OF MULTI-PURPOSE BUILDING, BARANGAY SAN MARTIN I, SAN JOSE DEL MONTE CITY, BULACAN is a DPWH-tracked public work in Bulacan 2nd DEO, Region III. Reported contract value: ₱4,751,002.29. Status: Past target date (DPWH On-Going). Contractor on record: EDELCRIZ CONST. Figures trace to dpwh.

Bulacan 2nd DEO, Region III
Region: Region III

Follow the peso

2 of 5 steps linked to this project, 1 at office level only. Links are automated matches unless marked confirmed.

  1. 1. GAA budget line

    FY2025 · ₱20,000

    Probable match · score 0.85

    DBM GAA source ↗
  2. 2. SARO / NCA release

    SARO SARO-ROXIII-25-0007502 · ₱7,279,122 · release to the district office, not itemized per project

    Possible match · score 0.60

    DBM release source ↗
  3. 3. PhilGEPS award

    Not found in PhilGEPS by contract ID 25CD0132 or title. The open PhilGEPS mirror does not include every DPWH notice.

  4. 4. DPWH progress + satellite

    87% reported · imagery 2021-02-02 → 2025-04-25

    Same record (DPWH contract ID)

    DPWH Transparency Portal source ↗
  5. 5. COA audit finding

    No COA finding names this project. COA audits DPWH by office each year; project-level findings are only linked when the report names the contract.

Been to this site?

Share a photo of what is there today. Faces and vehicle plates are blurred automatically, all photo metadata except the date and location is removed, and nothing is published until a moderator approves it.

Watch this project

Get a weekly email when this project changes: progress, new linked records or newly published anomaly flags.

Share card: CONSTRUCTION OF MULTI-PURPOSE BUILDING, BARANGAY SAN MARTIN I, SAN JOSE DEL MONTE CITY, BULACAN

Share this page

The card shows the public record facts and a QR code back to this page.

FacebookDownload image

Money Trail

1. Appropriation

Probable match · score 85%

UACS
18001
Amount
₱20,000,000.00 (GAA By-Object, amounts in ₱'000 × 1,000)
Program / description
Construction of Flood Control Structure, Pandayan-Saluysoy Creek, Barangay Saluysoy, Meycauayan City, Bulacan
GAA fiscal year
FY2025
DBM GAA source document

2. Allotment

Office-level release, not tied to this specific contract

SARO SARO-ROXIII-25-0007502

₱7,279,122.00 · FY2025

Released to Surigao del Norte State University (office-level, not project-specific). This SARO/NCA funds the office's programme; DBM listings do not tie it to this contract.

DBM SARO listing (source)

3. Procurement & Award

4. Implementation

Contract Amount

₱4,751,002.29

Progress

Past target date (DPWH On-Going)

Start Date

March 17, 2025

Target End

September 12, 2025

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.

Connected records

Where this project sits

Place (PSGC)
Region III (Central Luzon)BulacanCity of San Jose Del MonteSan Martin I
Storms whose wind field reached it
None on record (IBTrACS tracks).
Hazard exposure
No medium/high hazard on the mapped layers.Details in Hazard context above.Full hazard check →
El Niño outlook (province)
No PAGASA drought or dry flag for this province.El Niño readiness →

Exposure to a storm, hazard or drought outlook is context, not a finding about the project.