Buildings and Facilities17HH0124

IMPROVEMENT OF MULTI PURPOSE BUILDING, BRGY. CARRETA, CEBU CITY

IMPROVEMENT OF MULTI PURPOSE BUILDING, BRGY. CARRETA, CEBU CITY is a DPWH-tracked public work in Cebu City DEO, Region VII. Reported contract value: ₱2,399,288.16. Status: Reported complete (DPWH). Contractor on record: E V CABALLERO CONST. Figures trace to dpwh.

Cebu City DEO, Region VII
Region: Region VII

Satellite images processing — before/after tiles will appear here after the next batch run.

Money Trail

1. Appropriation

GAA FY2018 not yet loaded (source: DBM GAA)

2. Allotment

No SARO/NCA release rows linked to this project yet. See DBM release listings.

3. Procurement & Award

No PhilGEPS award linked in the link table for this contract yet.

Contractor

27 projects · ₱96.8M total · 0 flags

Other projects by this contractor

No sat.

CONVERGENCE AND SPECIAL SUPPORT PROGRAM-SUSTAINABLE INFRASTRUCTURE PROJECTS ALLEVIATING GAPS (SIPAG)-ACCESS ROADS AND/OR BRIDGES FROM THE NATIONAL ROAD/S LEADING TO MAJOR/STRATEGIC PUBLIC BUILDINGS/FACILITIES-CONSTRUCTION OF CONCRETE BRIDGE, SITIO CAMPO,

Cebu City DEO, Region VII

2024₱14.7M
Past target date (DPWH On-Going)
No sat.

CONSTRUCTION/MAINTENANCE OF FLOOD MITIGATION STRUCTURES AND DRAINAGE CONSTRUCTION OF FLOOD CONTROL STRUCTURES AT PAMINTAO RIVER ALONG CEBU NORTH HAGNAYA WHARF ROAD, BARANGAY TAYTAYAN, CITY OF BOGO

Cebu 4th DEO, Region VII

2018₱9.8M
Reported complete (DPWH)
No sat.

CONVERGENCE AND SPECIAL SUPPORT PROGRAM-SUSTAINABLE INFRASTRUCTURE PROJECTS ALLEVIATING GAPS (SIPAG)-ACCESS ROADS AND/OR BRIDGES FROM THE NATIONAL ROAD/S LEADING TO MAJOR/STRATEGIC PUBLIC BUILDINGS/FACILITIES-CONSTRUCTION OF ROAD, PACKAGE 2, BARANGAY LABA

Cebu City DEO, Region VII

2025₱9.7M
Reported complete (100% progress, DPWH status On-Going)
No sat.

CONVERGENCE AND SPECIAL SUPPORT PROGRAM-SUSTAINABLE INFRASTRUCTURE PROJECTS ALLEVIATING GAPS (SIPAG)-ACCESS ROADS AND/OR BRIDGES FROM THE NATIONAL ROAD/S LEADING TO MAJOR/ STRATEGIC PUBLIC BUILDINGS/FACILITIES-ROAD CONCRETING, BRGY. LABANGON, CEBU CITY, C

Cebu City DEO, Region VII

2023₱9.6M
Reported complete (DPWH)
No sat.

OO2: PROTECT LIVES AND PROPERTIES AGAINST MAJOR FLOODS - FLOOD MANAGEMENT PROGRAM - CONSTRUCTION / MAINTENANCE OF FLOOD MITIGATION STRUCTURES AND DRAINAGE SYSTEMS - CONSTRUCTION OF FLOOD MITIGATION STRUCTURE AT BRGY. LABANGON, CEBU CITY

Cebu City DEO, Region VII

2020₱5.5M
Reported complete (DPWH)
No sat.

CONSTRUCTION OF 2-UNITS UNIQUE WORKSHOP BUILDING, DOÑA LILING NEIS NEGAPATAN NHS, TABOGON, CEBU

Cebu 4th DEO, Region VII

2017₱5.2M
Reported complete (DPWH)
View all 27 projects →

4. Implementation

Contract Amount

₱2,399,288.16

Progress

Reported complete (DPWH)

Start Date

February 27, 2018

Target End

May 27, 2018

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.