Buildings and Facilities19OB0358

CONSTRUCTION OF MARIKINA POLYTECHNIC COLLEGE ACADEMIC BUILDING PHASE 3, MARIKINA CITY

CONSTRUCTION OF MARIKINA POLYTECHNIC COLLEGE ACADEMIC BUILDING PHASE 3, MARIKINA CITY is a DPWH-tracked public work in Metro Manila 1st DEO, National Capital Region. Reported contract value: ₱76,599,086.93. Status: Reported complete (DPWH). Contractor on record: BELL CONST. Figures trace to dpwh.

Metro Manila 1st DEO, National Capital Region
Region: National Capital Region

Money Trail

1. Appropriation

No matching GAA line found for this project in the FY2019 GAA. DBM GAA FY2019

2. Allotment

Office-level release, not tied to this specific contract

NCA NCA-ROIII-19-0021485

₱1,053,644.00 · FY2019

Released to Division of Nueva Ecija (office-level, not project-specific). This SARO/NCA funds the office's programme; DBM listings do not tie it to this contract.

DBM NCA listing (source)

3. Procurement & Award

No PhilGEPS award linked in the link table for this contract yet.

Contractor

C

128 projects · ₱5.5B total · 5 flags

4. Implementation

Contract Amount

₱76,599,086.93

Progress

Reported complete (DPWH)

Start Date

August 15, 2019

Target End

July 9, 2020

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.