Roads22HD0042

ROAD WIDENING ALONG CEBU NORTH HAGNAYA WHARF RD - K0085 + 928 - K0086 + 880, K 0085 + 928 - K0086 + 880, K0087 + 000 - K0087 + 289, K0087 + 406 - K0087 + 473, K0087 + 704 - K0088 + 257, K0098 + 845 - K0099 + 938, K0105 + 758 - K0106 + 001, BOGO, TABOGON,

ROAD WIDENING ALONG CEBU NORTH HAGNAYA WHARF RD - K0085 + 928 - K0086 + 880, K 0085 + 928 - K0086 + 880, K0087 + 000 - K0087 + 289, K0087 + 406 - K0087 + 473, K0087 + 704 - K0088 + 257, K0098 + 845 - K0099 + 938, K0105 + 758 - K0106 + 001, BOGO, TABOGON, is a DPWH-tracked public work in Cebu 4th DEO, Region VII. Reported contract value: ₱96,500,000.00. Status: Reported complete (DPWH). Contractor on record: DUROS DEVELOPMENT CORP. Figures trace to dpwh.

Cebu 4th DEO, Region VII
Region: Region VII

Follow the peso

1 of 5 steps linked to this project, 2 at office level only. Links are automated matches unless marked confirmed.

  1. 1. GAA budget line

    District-office budget line, FY2022 · ₱30,000 (shared by many projects, not this project's own line)

    Possible match · score 0.79

    DBM GAA source ↗
  2. 2. SARO / NCA release

    NCA NCA-BMB-C-22-0001976 · ₱171,653,146 · release to the district office, not itemized per project

    Possible match · score 0.61

    DBM release source ↗
  3. 3. PhilGEPS award

    Not found in PhilGEPS by contract ID 22HD0042 or title. The open PhilGEPS mirror does not include every DPWH notice.

  4. 4. DPWH progress + satellite

    100% reported · imagery 2019-04-20 → 2025-10-05

    Same record (DPWH contract ID)

    DPWH Transparency Portal source ↗
  5. 5. COA audit finding

    No COA finding names this project. COA audits DPWH by office each year; project-level findings are only linked when the report names the contract.

Unit-cost benchmark · Road, cost per km (widening)

₱23,258,617 per km= 0.6x the Region VII median (n=130)

Contract cost ₱96,500,000 ÷ 4.149 km read from the DPWH title (“K0085 + 928 - K0086 + 880; K 0085 + 928 - K0086 + 880; K0087 + 000 - K0087 + 289; K0087 + 406 - K0087 + 473; K0087 + 704 - K0088 + 257; K0098 + 845 - K0099 + 938; K0105 + 758 - K0106 + 001”; K-post / station range length). National percentile: 14. Higher unit cost can have legitimate causes (terrain, design, scope not stated in the title); this is a comparison, not a finding. Methodology

Been to this site?

Share a photo of what is there today. Faces and vehicle plates are blurred automatically, all photo metadata except the date and location is removed, and nothing is published until a moderator approves it.

Watch this project

Get a weekly email when this project changes: progress, new linked records or newly published anomaly flags.

Share card: ROAD WIDENING ALONG CEBU NORTH HAGNAYA WHARF RD - K0085 + 928 - K0086 + 880, K 0085 + 928 - K0086 + 880, K0087 + 000 - K0087 + 289, K0087 + 406 - K0087 + 473, K0087 + 704 - K0088 + 257, K0098 + 845 - K0099 + 938, K0105 + 758 - K0106 + 001, BOGO, TABOGON,

Share this page

The card shows the public record facts and a QR code back to this page.

FacebookDownload image

Money Trail

1. Appropriation

Possible match · score 79%

UACS
18001
Amount
₱30,000,000.00 (GAA By-Object, amounts in ₱'000 × 1,000)
Program / description
Construction of Pasil Flood Control, Oslob, Cebu
GAA fiscal year
FY2022
DBM GAA source document

2. Allotment

Office-level release, not tied to this specific contract

NCA NCA-BMB-C-22-0001976

₱171,653,146.00 · FY2022

Released to Cebu 4th DEO (office-level, not project-specific). This SARO/NCA funds the office's programme; DBM listings do not tie it to this contract.

DBM NCA listing (source)

3. Procurement & Award

No PhilGEPS award linked in the link table for this contract yet.

Contractor

A

260 projects · ₱10.6B total · 0 flags

Other projects by this contractor

No sat.

CONSTRUCTION/REPAIR /REHABILITATION/IMPROVEMENT OF VARIOUS INFRASTRUCTURE INCLUDING LOCAL PROJECTS, CONCRETING/IMPROVEMENT OF BANTAYAN-MADREDIJOS ROAD SECTION STA. 0+000-STA. 13+032

Region VII, Region VII

2016₱238.0M
Reported complete (DPWH)
No sat.

CONVERGENCE AND SPECIAL SUPPORT PROGRAM, SUSTAINABLE INFRASTRUCTURE PROJECTS ALLEVIATING GAPS (SIPAG) - MULTI-PURPOSE BUILDINGS/ FACILITIES TO SUPPORT SOCIAL SERVICES, CONSTRUCTION OF MULTIPURPOSE BUILDING (LILOAN, MUNICIPAL HALL), LILOAN, CEBU

Region VII, Region VII

2023₱193.0M
Past target date (DPWH On-Going)
No sat.

LOCAL PROGRAM, CONSTRUCTION/REPAIR/REHABILITATION/IMPROVEMENT OF VARIOUS INFRASTRUCTURE INCLUDING LOCAL PROJECTS BUILDINGS AND OTHER STRUCTURES, MULTIPURPOSE/FACILITIES, CONSTRUCTION/REHABILITATION OF MULTI-PURPOSE BUILDING (MUNICIPAL HALL), BARANGAY POBL

Region VII, Region VII

2021₱187.2M
Reported complete (DPWH)
No sat.

MFO-1 NATIONAL ROAD NETWORK SERVICES, ASSET PRESERVATION OF NATIONAL ROADS-REHABILITATION/RECONSTRUCTION OF NATIONAL ROADS WITH SLIPS/SLOPE COLLAPSE, AND LANDSLIDE CEBU-BALAMBAN TRANSCENTRAL HIGHWAY, K0036+790-K0036+880; K0031+910-K0031+985

Region VII, Region VII

2017₱162.1M
Reported complete (DPWH)
No sat.

ORGANIZATIONAL OUTCOME 1: ENSURE SAFE AND RELIABLE NATIONAL ROAD SYSTEM, ASSET PRESERVATION PROGRAM - PREVENTIVE MAINTENANCE - SECONDARY ROADS, CEBU NORTH HAGNAYA WHARF RD - K0098 + 829 - K0099 + 889, K0102 + 000 - K0102 + 680, K0105 + 658 - K0105 + 993

Region VII, Region VII

2025₱158.8M
Past target date (DPWH On-Going)
No sat.

ASSET PRESERVATION-PREVENTIVE MAINTENANCE-SECONDARY ROADS - CALUBIAN JCT-SN ISIDRO-TABANGO-VILLABA-PALOMPON RD K1042+285-K1046+979, VILLABA, LEYTE

Leyte 3rd DEO, Region VIII

2025₱142.8M
Reported complete (100% progress, DPWH status On-Going)
View all 260 projects →

4. Implementation

Contract Amount

₱96,500,000.00

Progress

Reported complete (DPWH)

Start Date

March 24, 2022

Target End

January 21, 2023

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.

Connected records

Where this project sits

Place (PSGC)
Region VII (Central Visayas)CebuCity of BogoCogon
Storms whose wind field reached it
None on record (IBTrACS tracks).
Hazard exposure
No medium/high hazard on the mapped layers.Details in Hazard context above.Full hazard check →
El Niño outlook (province)
No PAGASA drought or dry flag for this province.El Niño readiness →

Exposure to a storm, hazard or drought outlook is context, not a finding about the project.