Water Provision and Storage17P00049

CONSTRUCTION/REHABILITATION OF WATER SUPPLY/SEPTAGE AND SEWERAGE/RAIN WATER COLLECTORS - CONSTRUCTION OF RAIN HARVESTING FACILITY, BAGUIO CITY

CONSTRUCTION/REHABILITATION OF WATER SUPPLY/SEPTAGE AND SEWERAGE/RAIN WATER COLLECTORS - CONSTRUCTION OF RAIN HARVESTING FACILITY, BAGUIO CITY is a DPWH-tracked public work in Cordillera Administrative Region, Cordillera Administrative Region. Reported contract value: ₱123,195,013.96. Status: Reported complete (DPWH). Contractor on record: GOLDRICH CONST. Figures trace to dpwh.

Cordillera Administrative Region, Cordillera Administrative Region
Region: Cordillera Administrative Region

Satellite images processing — before/after tiles will appear here after the next batch run.

Money Trail

1. Appropriation

No matching GAA line found for this project in the FY2016 GAA. DBM GAA FY2016

2. Allotment

No matching SARO/NCA release found for this project. Source: DBM SARO/NCA listings.

3. Procurement & Award

No PhilGEPS award linked in the link table for this contract yet.

Contractor

122 projects · ₱6.1B total · 0 flags

Other projects by this contractor

No sat.

ORGANIZATIONAL OUTCOME 1: ENSURE SAFE AND RELIABLE NATIONAL ROAD SYSTEM NETWORK DEVELOPMENT - PAVING OF UNPAVED ROADS (TERTIARY ROADS) CLAVERIA-CALANASAN-KABUGAO RD., K0678+899 - K0682+045

Cordillera Administrative Region, Cordillera Administrative Region

2018₱159.8M
Reported complete (DPWH)
No sat.

CONSTRUCTION/IMPROVEMENT OF ACCESS ROADS LEADING TO TRADES, INDUSTRIES AND ECONOMIC ZONES, POBLACION-PUGUIL-TUBADAY ROAD, CONNECTING BALAOAN-SANTOL ROAD IN SUPPORT TO SOFT BROOM INDUSTRY AND OTHER HIGH VALUE AGRICULTURAL PRODUCTS, SANTOL, LA UNION

Region I, Region I

2018₱144.7M
Reported complete (DPWH)
No sat.

CONTRACT PACKAGE 1: CONST/REH OF FLOOD MITIGATION FACILITIES WITHIN MAJOR RIVER BASINS AND PRINCIPAL RIVERS CONST. OF FLOOD MITIGATION FACILITIES ALONG A. BALILI RIVER (MAIN) STA. 1+297-STA. 1+400 B. ASIN-GALLANO RIVER STA. 2+240-STA. 2+788

Baguio City DEO, Cordillera Administrative Region

2025₱139.8M
Past target date (DPWH On-Going)
No sat.

CONTRACT PACKAGE 1: A. PREVENTIVE MAINTENANCE -SECONDARY ROADS: 1. ASIN RD. K0305+(-535), K0305+000-K0306+541, (S04722LZ) CHAINAGE 000-CHAINAGE 1552. LOAKAN RD. K0249+875-K0250+096, K0250+380-K0250+842 3. MAGSAYSAY AVE (TRINIDAD RD) - (S00522LZ) CHAINAGE

Baguio City DEO, Cordillera Administrative Region

2023₱138.1M
Reported complete (DPWH)
No sat.

ORGANIZATIONAL OUTCOME 1: ENSURE SAFE AND RELIABLE NATIONAL ROAD SYSTEM - NETWORK DEVELOPMENT PROGRAM - CONSTRUCTION OF MISSING LINKS/NEW ROADS BAGUIO - LA TRINIDAD - ITOGON - SABLAN - TUBA AND TUBLAY, KAMOG JCT. - CALOT - PAPPA - BAGONG - BALLUAY - TUEL

Cordillera Administrative Region, Cordillera Administrative Region

2020₱133.0M
Reported complete (DPWH)
No sat.

CONTRACT PACKAGE 6: REH/RECONST. OF ROADS WITH SLIPS, SLOPE COLLAPSE, AND LANDSLIDE: A. SECONDARY ROADS: 1. PMA RD. K0249+480-K0249+598 B. TERTIARY ROADS: 1. EASTERNLINK CIRCUM RD. K0247+930-K0247+980 2. PMA CUT-OFF RD. 3- (S05054LZ): CH. 1600 - CH. 1700

Baguio City DEO, Cordillera Administrative Region

2024₱124.7M
Reported complete (DPWH)
View all 122 projects →

4. Implementation

Contract Amount

₱123,195,013.96

Progress

Reported complete (DPWH)

Start Date

May 31, 2017

Target End

December 1, 2018

5. Audit