Flood Control and Drainage19JA0023

CONSTRUCTION OF FLOOD CONTROL STRUCTURE ALONG AYALA RIVER, AYALA SECTION, ZAMBOANGA CITY

CONSTRUCTION OF FLOOD CONTROL STRUCTURE ALONG AYALA RIVER, AYALA SECTION, ZAMBOANGA CITY is a DPWH-tracked public work in Zamboanga City 2nd DEO, Region IX. Reported contract value: ₱14,394,284.44. Status: Reported complete (DPWH). Contractor on record: LONG ISLAND BUILDERS. Figures trace to dpwh.

Zamboanga City 2nd DEO, Region IX
Region: Region IX

Follow the peso

2 of 5 steps linked to this project, 1 at office level only. Links are automated matches unless marked confirmed.

  1. 1. GAA budget line

    No GAA line found for this project's office and year. The GAA lists budgets by program and office, not always by project.

  2. 2. SARO / NCA release

    SARO SARO-ROIX-19-0025380 · ₱476,000 · release to the district office, not itemized per project

    Possible match · score 0.70

    DBM release source ↗
  3. 3. PhilGEPS award

    ₱14,394,364 · LONG ISLAND BUILDERS & CONSTRUCTION

    Confirmed (exact contract ID) · score 1.00

    PhilGEPS source ↗
  4. 4. DPWH progress + satellite

    100% reported · imagery 2015-05-10 → 2024-12-30

    Same record (DPWH contract ID)

    DPWH Transparency Portal source ↗
  5. 5. COA audit finding

    No COA finding names this project. COA audits DPWH by office each year; project-level findings are only linked when the report names the contract.

Site vs flood hazard · Project NOAH 100-year map

High flood hazard · Zamboanga del Sur

Based on the coordinates published with the DPWH record and NOAH file ZamboangaDelSur.zip. Pins are sometimes placed at the town center rather than the site. NOAH data (ODbL) · Need vs spending by province

Been to this site?

Share a photo of what is there today. Faces and vehicle plates are blurred automatically, all photo metadata except the date and location is removed, and nothing is published until a moderator approves it.

Watch this project

Get a weekly email when this project changes: progress, new linked records or newly published anomaly flags.

Share card: CONSTRUCTION OF FLOOD CONTROL STRUCTURE ALONG AYALA RIVER, AYALA SECTION, ZAMBOANGA CITY

Share this page

The card shows the public record facts and a QR code back to this page.

FacebookDownload image

Money Trail

1. Appropriation

No matching GAA line found for this project in the FY2019 GAA. DBM GAA FY2019

2. Allotment

Office-level release, not tied to this specific contract

SARO SARO-ROIX-19-0025380

₱476,000.00 · FY2019

Released to Zamboanga City District Engineering Office (office-level, not project-specific). This SARO/NCA funds the office's programme; DBM listings do not tie it to this contract.

DBM SARO listing (source)

3. Procurement & Award

Confirmed (exact contract ID) · 100%

CONSTRUCTION PROJECT

₱14,394,364.06 · LONG ISLAND BUILDERS & CONSTRUCTION

Award / contract ref: 19JA0023

Contractor

B

275 projects · ₱5.6B total · 0 flags

Other projects by this contractor

No sat.

CONSTRUCTION/ MAINTENANCE OF FLOOD MITIGATION STRUCTURES AND DRAINAGE SYSTEMS - CONSTRUCTION OF FLOOD CONTROL STRUCTURE ALONG PULIRAN RIVER, PULIRAN BR. SECTION PACKAGE 2, SIBUCO, ZAMBOANGA DEL NORTE

Region IX, Region IX

2024₱164.0M
Past target date (DPWH On-Going)
No sat.

ACCESS ROADS AND/OR BRIDGES FROM THE NATIONAL ROAD/S LEADING TO MAJOR/STRATEGIC PUBLIC BUILDINGS/FACILITIES - REHABILITATION OF ROAD, BARANGAY BALAKAN-BARANGAY CALUCAP ROAD, SALUG, ZAMBOANGA DEL NORTE

Region IX, Region IX

2025₱153.0M
Past target date (DPWH On-Going)

CONSTRUCTION / REHABILITATION OF FLOOD MITIGATION FACILITIES WITHIN MAJOR RIVER BASINS AND PRINCIPAL RIVERS - CONSTRUCTION OF FLOOD CONTROL STRUCTURE ALONG SIOCON RIVER (DOWNSTREAM), SIOCON, ZAMBOANGA DEL NORTE, PACKAGE 2

Region IX, Region IX

2024₱137.9M
Reported complete (100% progress, DPWH status On-Going)
No sat.

CONSTRUCTION/MAINTENANCE OF FLOOD MITIGATION STRUCTURES AND DRAINAGE SYSTEMS - CONSTRUCTION OF FLOOD CONTROL STRUCTURE ALONG SALUG RIVER AT SALUG BR. SECTION (B00528MN) ALONG SINDANGAN-LILOY ROAD (S01142MN), SALUG, ZAMBOANGA DEL NORTE, PACKAGE 1

Region IX, Region IX

2024₱128.8M
Past target date (DPWH On-Going)
No sat.

CONSTRUCTION/MAINTENANCE OF FLOOD MITIGATION STRUCTURES AND DRAINAGE SYSTEMS - CONSTRUCTION OF FLOOD CONTROL STRUCTURE WITH ESPLANADE AT SALUG BRIDGE (B00528MN), SALUG, ZAMBOANGA DEL NORTE

Region IX, Region IX

2023₱109.9M
Past target date (DPWH On-Going)

CONSTRUCTION OF FLOOD CONTROL STRUCTURE ALONG KIPIT RIVER, GUTALAC, ZAMBOANGA DEL NORTE (UPSTREAM) STA. 0 + 204 - 0 + 604

Zamboanga del Norte 3rd DEO, Region IX

2024₱95.5M
Reported complete (100% progress, DPWH status On-Going)
View all 275 projects →

4. Implementation

Contract Amount

₱14,394,284.44

Progress

Reported complete (DPWH)

Start Date

July 10, 2019

Target End

December 27, 2019

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.

Connected records

Where this project sits

Place (PSGC)
Region IX (Zamboanga Peninsula)City of ZamboangaAyala
Storms whose wind field reached it
None on record (IBTrACS tracks).
Hazard exposure
Flood (100-yr rain)Storm surgeDetails in Hazard context above.Full hazard check →
El Niño outlook (province)
No province on record.El Niño readiness →

Exposure to a storm, hazard or drought outlook is context, not a finding about the project.