Roads20PJ0042

LOCAL INFRASTRUCTURE PROGRAM - CONSTRUCTION OF ROADS, MAJLONG, AGUINALDO, IFUGAO

LOCAL INFRASTRUCTURE PROGRAM - CONSTRUCTION OF ROADS, MAJLONG, AGUINALDO, IFUGAO is a DPWH-tracked public work in Ifugao 2nd DEO, Cordillera Administrative Region. Reported contract value: ₱4,849,648.99. Status: Reported complete (DPWH). Contractor on record: CNRJ CONST. Figures trace to dpwh.

Ifugao 2nd DEO, Cordillera Administrative Region
Region: Cordillera Administrative Region

Satellite images processing — before/after tiles will appear here after the next batch run.

Money Trail

1. Appropriation

Probable match · score 85%

UACS
18001
Amount
₱20,000,000.00 (GAA By-Object, amounts in ₱'000 × 1,000)
Program / description
Construction of Halag Flood Control, Halag, Aguinaldo, Ifugao
GAA fiscal year
FY2020
DBM GAA source document

2. Allotment

Office-level release, not tied to this specific contract

SARO SARO-ROX-20-0015050

₱123,000.00 · FY2020

Released to Division of Iligan City (office-level, not project-specific). This SARO/NCA funds the office's programme; DBM listings do not tie it to this contract.

DBM SARO listing (source)

3. Procurement & Award

No PhilGEPS award linked in the link table for this contract yet.

Contractor

C

18 projects · ₱65.4M total · 0 flags

Other projects by this contractor

No sat.

23PJ0053: BASIC EDUCATIONAL FACILITIES FUND (BEFF)-BATCH 1: CONSTRUCTION OF 1STY2CL, BUNINAN PS, MAYOYAO, IFUGAO

Ifugao 2nd DEO, Cordillera Administrative Region

2023₱5.0M
Reported complete (DPWH)
No sat.

24PJ0049: BASIC EDUCATIONAL FACILITIES FUND (BEFF): CONSTRUCTION OF 1-STOREY 2- CLASSROOM SCHOOL BUILDING IN RUFINO I. CHUNGALAO SCIENCE HIGH SCHOOL, BARANGAY MONGGAYANG, AGUINALDO, IFUGAO

Ifugao 2nd DEO, Cordillera Administrative Region

2024₱5.0M
Reported complete (DPWH)
No sat.

21PJ0049: LOCAL INFRASTRUCTURE PROGRAM-CONSTRUCTION OF BARANGAY MAPAWOY TO BARANGAY BONGAN ROAD, MAPAWOY, MAYOYAO, IFUGAO

Ifugao 2nd DEO, Cordillera Administrative Region

2021₱5.0M
Reported complete (DPWH)
No sat.

25PJ0040: CONVERGENCE AND SPECIAL SUPPORT PROGRAM-BASIC INFRASTRUCTURE PROGRAM (BIP) - MULTI-PURPOSE BUILDINGS/ FACILITIES TO SUPPORT SOCIAL SERVICES-CONSTRUCTION OF MULTI-PURPOSE BUILDING, BARANGAY UBAO, AGUINALDO, IFUGAO

Ifugao 2nd DEO, Cordillera Administrative Region

2025₱4.9M
Reported complete (100% progress, DPWH status On-Going)
No sat.

CONCRETING OF BARANGAY AWAYAN FARM TO MARKET ROAD, BARANGAY AWAYAN, AGUINALDO, IFUGAO

Ifugao 2nd DEO, Cordillera Administrative Region

2019₱4.9M
Reported complete (DPWH)
No sat.

25PJ0074: CONVERGENCE AND SPECIAL SUPPORT PROGRAM-SUSTAINABLE INFRASTRUCTURE PROJECTS ALLEVIATING GAPS (SIPAG) - ACCESS ROADS AND/OR BRIDGES FROM THE NATIONAL ROADS CONNECTING TO INDIGENOUS PEOPLE (IP) COMMUNITIES-CONSTRUCTION OF PUNGOD - GUWATIG TO POMOH

Ifugao 2nd DEO, Cordillera Administrative Region

2025₱4.9M
Past target date (DPWH On-Going)
View all 18 projects →

4. Implementation

Contract Amount

₱4,849,648.99

Progress

Reported complete (DPWH)

Start Date

February 17, 2020

Target End

August 19, 2020

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.