Roads24IH0094

CONCRETING OF BRGY. CHITONGCO TO SITIO PAMISWAKAN FMR, MONDRAGON, NORTHERN SAMAR

CONCRETING OF BRGY. CHITONGCO TO SITIO PAMISWAKAN FMR, MONDRAGON, NORTHERN SAMAR is a DPWH-tracked public work in Northern Samar 1st DEO, Region VIII. Reported contract value: ₱24,863,305.49. Status: Past target date (DPWH On-Going). Contractor on record: SMU CONST AND SUPPLY. Figures trace to dpwh.

Northern Samar 1st DEO, Region VIII
Region: Region VIII

Money Trail

1. Appropriation

Possible match · score 84%

UACS
18001
Amount
₱30,000,000.00 (GAA By-Object, amounts in ₱'000 × 1,000)
Program / description
Construction of Flood Mitigation Structure, Brgy. Rawis, Laoang, Northern Samar
GAA fiscal year
FY2024
DBM GAA source document

2. Allotment

Office-level release, not tied to this specific contract

NCA NCA-BMB-C-24-0001210

₱10,522,000.00 · FY2024

Released to Northern Samar 1st DEO (office-level, not project-specific). This SARO/NCA funds the office's programme; DBM listings do not tie it to this contract.

DBM NCA listing (source)

3. Procurement & Award

No PhilGEPS award linked in the link table for this contract yet.

4. Implementation

Contract Amount

₱24,863,305.49

Progress

Past target date (DPWH On-Going)

Start Date

September 5, 2024

Target End

May 19, 2025

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.