GAA 2025 SSP25RG0120

BASIC INFRASTRUCTURE PROGRAM (BIP) MULTI-PURPOSE BUILDINGS/ FACILITIES TO SUPPORT SOCIAL SERVICES CONSTRUCTION (COMPLETION) OF MULTI-PURPOSE BUILDING, BARANGAY HIBAIYO, GUIHULNGAN CITY, NEGROS ORIENTAL

BASIC INFRASTRUCTURE PROGRAM (BIP) MULTI-PURPOSE BUILDINGS/ FACILITIES TO SUPPORT SOCIAL SERVICES CONSTRUCTION (COMPLETION) OF MULTI-PURPOSE BUILDING, BARANGAY HIBAIYO, GUIHULNGAN CITY, NEGROS ORIENTAL is a DPWH-tracked public work in Negros Oriental 1st DEO, Negros Island Region. Reported contract value: ₱1,950,000.00. Status: Reported complete (100% progress, DPWH status On-Going). Contractor on record: ALEXANDRIA CONST AND SUPPLY. Figures trace to dpwh.

Negros Oriental 1st DEO, Negros Island Region
Region: Negros Island Region

Satellite images processing — before/after tiles will appear here after the next batch run.

Money Trail

1. Appropriation

Probable match · score 85%

UACS
18001
Amount
₱36,415,000.00 (GAA By-Object, amounts in ₱'000 × 1,000)
Program / description
Construction of Flood Control Structure along Bitoclan River, Guihulngan City, Negros Oriental
GAA fiscal year
FY2025
DBM GAA source document

2. Allotment

Office-level release, not tied to this specific contract

NCA NCA-BMB-D-25-0016891

₱1,680,345.00 · FY2025

Source

3. Procurement & Award

No PhilGEPS award linked in the link table for this contract yet.

Contractor

23 projects · ₱99.6M total · 0 flags

Other projects by this contractor

No sat.

CONCRETING OF BRGY. TIMBAO FMR PHASE III, BRGY. TIMBAO, BACONG, NEGROS ORIENTAL

Negros Oriental 3rd DEO, Negros Island Region

2024₱14.9M
Reported complete (DPWH)
No sat.

Construction of Flood Control along Kinayan River, Guihulngan City, Negros Oriental

CITY OF GUIHULNGAN (NEGROS ORIENTAL), NEGROS ORIENTAL, Region VII

2024₱14.6M
Reported complete (DPWH)
No sat.

BASIC INFRASTRUCTURE PROGRAM (BIP): MULTI-PURPOSE BUILDINGS/ FACILITIES TO SUPPORT SOCIAL SERVICES: CONSTRUCTION (COMPLETION) OF MULTI-PURPOSE BUILDING, NORTH POBLACION, BACONG, NEGROS ORIENTAL

Negros Oriental 3rd DEO, Negros Island Region

2022₱9.4M
Reported complete (DPWH)
No sat.

BASIC INFRASTRUCTURE PROGRAM (BIP): MULTI-PURPOSE BUILDINGS/ FACILITIES TO SUPPORT SOCIAL SERVICES: CONSTRUCTION OF MULTI-PURPOSE BUILDINGS AT DISTRICT 1, DAUIN, NEGROS ORIENTAL

Negros Oriental 3rd DEO, Negros Island Region

2022₱5.4M
Reported complete (DPWH)
No sat.

CONVERGENCE AND SPECIAL SUPPORT PROGRAM: BASIC INFRASTRUCTURE PROGRAM (BIP): ACCESS ROADS AND/OR BRIDGES FROM THE NATIONAL ROAD/S LEADING TO MAJOR/ STRATEGIC PUBLIC BUILDINGS/FACILITIES: CONSTRUCTION OF ROAD IN BRGY. CAMBUCAD, VALENCIA, NEGROS ORIENTAL

Negros Oriental 3rd DEO, Negros Island Region

2023₱5.0M
Reported complete (DPWH)
No sat.

BASIC INFRASTRUCTURE PROGRAM (BIP): ACCESS ROADS AND/OR BRIDGES FROM THE NATIONAL ROAD/S LEADING TO MAJOR/ STRATEGIC PUBLIC BUILDINGS/FACILITIES: IMPROVEMENT OF ROAD, SITO ILAWOD AND BARANGAY TUBOD, BAYAWAN CITY, NEGROS OCCIDENTAL

Negros Oriental 3rd DEO, Negros Island Region

2022₱5.0M
Reported complete (DPWH)
View all 23 projects →

4. Implementation

Contract Amount

₱1,950,000.00

Progress

Reported complete (100% progress, DPWH status On-Going)

Start Date

July 7, 2025

Target End

August 31, 2025

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.