Buildings and Facilities23J00079

CONSTRUCTION OF LANTAWAN MUNICIPAL POLICE STATION BUILDING, LANTAWAN, BASILAN, PHASE II

CONSTRUCTION OF LANTAWAN MUNICIPAL POLICE STATION BUILDING, LANTAWAN, BASILAN, PHASE II is a DPWH-tracked public work in Region IX, Region IX. Reported contract value: ₱4,809,502.33. Status: Reported complete (100% progress, DPWH status On-Going). Contractor on record: RR-JAM CONST. Figures trace to dpwh.

Region IX, Region IX
Region: Region IX

Satellite images processing — before/after tiles will appear here after the next batch run.

Money Trail

1. Appropriation

No GAA appropriation line matched for this project at current confidence thresholds.

2. Allotment

No SARO/NCA release rows linked to this project yet. See DBM release listings.

3. Procurement & Award

No PhilGEPS award linked in the link table for this contract yet.

Contractor

23 projects · ₱395.7M total · 0 flags

Other projects by this contractor

No sat.

SIPAG - ACCESS ROADS AND/OR BRIDGES FROM THE NATIONAL ROAD/S LEADING TO MAJOR/STRATEGIC PUBLIC BUILDINGS/FACILITIES - CONSTRUCTION OF ROAD, BARANGAY LANDANG GUA, ZAMBOANGA CITY, ZAMBOANGA DEL SUR

Zamboanga City 2nd DEO, Region IX

2025₱47.7M
Past target date (DPWH On-Going)
No sat.

SUSTAINABLE INFRASTRUCTURE ALLEVIATING GAPS (SIPAG) - ACCESS ROADS AND/OR BRIDGES FROM THE NATIONAL ROAD/S LEADING TO MAJOR/STRATEGIC PUBLIC BUILDINGS/FACILITIES - CONSTRUCTION OF ROAD, BARANGAY PASILMANTA, ZAMBOANGA CITY, ZAMBOANGA DEL SUR

Zamboanga City 2nd DEO, Region IX

2025₱47.6M
Past target date (DPWH On-Going)
No sat.

ACCESS ROADS AND/OR BRIDGES FROM THE NATIONAL ROAD/S LEADING TO MAJOR/STRATEGIC PUBLIC BUILDINGS/FACILITIES - CONSTRUCTION OF ROAD, SIRATANG-SUBAH MAMAH, LANGUYAN, TAWI-TAWI

Region IX, Region IX

2024₱33.7M
Past target date (DPWH On-Going)
No sat.

CONSTRUCTION OF THREE (3) STORY NINE (9) CLASSROOM SCHOOL BUILDING AT LUMBANGAN ELEMENTARY SCHOOL, BARANGAY LUMBANGAN, ZAMBOANGA CITY, ZAMBOANGA DEL SUR

Zamboanga City 2nd DEO, Region IX

2023₱29.7M
Past target date (DPWH On-Going)
No sat.

IMPROVEMENT OF ROAD, BARANGAY MARANG-MARANG TO BRGY. LUKBUTON, ISABELA CITY, BASILAN

Isabela City DEO, Region IX

2023₱29.4M
Reported complete (DPWH)
No sat.

CONSTRUCTION/IMPROVEMENT OF ACCESS ROADS LEADING TO DECLARED TOURISM DESTINATIONS (TOURISM ROAD INFRASTRUCTURE PROGRAM - TRIP) - BRGY. LUKBUTON TO BRGY. PANIGAYAN LEADING TO WHITE BEACH, MALAMAWI ISLAND, ISABELA CITY, BASILAN

Region IX, Region IX

2023₱27.9M
Reported complete (DPWH)
View all 23 projects →

4. Implementation

Contract Amount

₱4,809,502.33

Progress

Reported complete (100% progress, DPWH status On-Going)

Start Date

April 11, 2023

Target End

August 8, 2023

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.