Flood Control and Drainage24JD0009

CONSTRUCTION OF FLOOD CONTROL STRUCTURE ALONG PALANDOK RIVER (UPSTREAM) STA. 0+000.00 - STA. 0+400.00, LEON B. POSTIGO, ZAMBOANGA DEL NORTE

CONSTRUCTION OF FLOOD CONTROL STRUCTURE ALONG PALANDOK RIVER (UPSTREAM) STA. 0+000.00 - STA. 0+400.00, LEON B. POSTIGO, ZAMBOANGA DEL NORTE is a DPWH-tracked public work in Zamboanga del Norte 3rd DEO, Region IX. Reported contract value: ₱95,037,218.23. Status: Reported complete (100% progress, DPWH status On-Going). Contractor on record: EDANNA CONST. Figures trace to dpwh.

Zamboanga del Norte 3rd DEO, Region IX
Region: Region IX

Money Trail

1. Appropriation

Probable match · score 91%

UACS
18001
Amount
₱15,000,000.00 (GAA By-Object, amounts in ₱'000 × 1,000)
Program / description
Rehabilitation of Flood Control Structure along Talinga River ( Upstream ) , Talinga, Leon B. Postigo, Zamboanga del Norte
GAA fiscal year
FY2024
DBM GAA source document

2. Allotment

Office-level release, not tied to this specific contract

NCA NCA-ROXI-24-0016030

₱6,897,380.00 · FY2024

Released to Davao del Sur District Engineering Office (office-level, not project-specific). This SARO/NCA funds the office's programme; DBM listings do not tie it to this contract.

DBM NCA listing (source)

3. Procurement & Award

No PhilGEPS award linked in the link table for this contract yet.

Contractor

B

44 projects · ₱1.1B total · 0 flags

4. Implementation

Contract Amount

₱95,037,218.23

Progress

Reported complete (100% progress, DPWH status On-Going)

Start Date

April 29, 2024

Target End

March 26, 2025

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.