Roads23J00131

CONSTRUCTION OF BY-PASS AND DIVERSION ROADS - BUENAVISTA-BOLONG BY-PASS ROAD, PACKAGE 8, ZAMBOANGA CITY

CONSTRUCTION OF BY-PASS AND DIVERSION ROADS - BUENAVISTA-BOLONG BY-PASS ROAD, PACKAGE 8, ZAMBOANGA CITY is a DPWH-tracked public work in Region IX, Region IX. Reported contract value: ₱142,967,771.55. Status: Past target date (DPWH On-Going). Contractor on record: 2M CONST. Figures trace to dpwh.

Region IX, Region IX
Region: Region IX

Money Trail

1. Appropriation

No GAA appropriation line matched for this project at current confidence thresholds.

2. Allotment

No SARO/NCA release rows linked to this project yet. See DBM release listings.

3. Procurement & Award

No PhilGEPS award linked in the link table for this contract yet.

Contractor

101 projects · ₱4.1B total · 0 flags

Other projects by this contractor

View all 101 projects →

4. Implementation

Contract Amount

₱142,967,771.55

Progress

Past target date (DPWH On-Going)

Start Date

September 20, 2023

Target End

September 15, 2024

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.