CONCRETING OF BRGY. CABUNGAAN FMR, NAVAL, BILIRAN

CONCRETING OF BRGY. CABUNGAAN FMR, NAVAL, BILIRAN is a DPWH-tracked public work in Biliran DEO, Region VIII. Reported contract value: ₱11,927,376.57. Status: Past target date (DPWH On-Going). Contractor on record: RMA BUILDERS. Figures trace to dpwh.

Biliran DEO, Region VIII
Region: Region VIII

Satellite images processing — before/after tiles will appear here after the next batch run.

Money Trail

1. Appropriation

Possible match · score 84%

UACS
18001
Amount
₱5,000,000.00 (GAA By-Object, amounts in ₱'000 × 1,000)
Program / description
Construction of Flood Control Structure, Barangay Anislagan, Naval, Biliran
GAA fiscal year
FY2023
DBM GAA source document

2. Allotment

Office-level release, not tied to this specific contract

SARO SARO-BMB-D-23-001938

₱4,114,500.00 · FY2023

Released to 1300085 Home Office - (office-level, not project-specific). This SARO/NCA funds the office's programme; DBM listings do not tie it to this contract.

DBM SARO listing (source)

3. Procurement & Award

No PhilGEPS award linked in the link table for this contract yet.

Contractor

F

72 projects · ₱761.0M total · 0 flags

4. Implementation

Contract Amount

₱11,927,376.57

Progress

Past target date (DPWH On-Going)

Start Date

March 19, 2023

Target End

November 11, 2023

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.